Quantity of cement in kgs for different proportions and
different thickness in plastering work per 1 sq.m. And how
to estimate this quantities.
Answer Posted / manoj patel
Theoritically;
> for mix Proportion 1:3;
> 12mm thick,
> 1m2 plaster will require 6.20kg of cement.
Assumption - No Wastage
Plaster Yield - 70%
| Is This Answer Correct ? | 19 Yes | 5 No |
Post New Answer View All Answers
I HAVE APPLIED FOR 20TH UES ARMY. I WANTED TO KNOW WHEN WILL I RECEIVE CALL LETTER FOR THE SAME.
yasser arfatcompleted his degree in civil from which university
how many minimum admixtures are used in water froofing structures
How to do base isolation for RC framed structure using ETABS software?
What is missing report and how to prepare
I want to know the material required per Square foot in rcc roof i.e.Steel ,Cement,
How can we convert weight batch to volume batch for m30 mix
what is the price of a cubic meter of concrete on international market?
How to calculate quantity of cement , sand and granite from concrete mix ratio and volume of work
How do you compute moisture correction using the parameters gathered from Nuclear Density Gauge Apparatus and the moisture contents results from the lab.?
cement mortor 1:5 for 30 m2 12 mm tk plastering so how to calcualte its rate
What happens when,in Prestressed girder the HDPE duct and cone size is provided more than required? (technical answer expected)
At what point does a circle start losing area when being flattened?
How to come 1.54 from dry to wet concrete?
I have an plot with area 35*47 = 182.77 sq yards. Out of this iam planning to construct house with 1350 sqfeet each floor .iwanted to build a G+2 house.Need cost estimation for each item