Quantity of cement in kgs for different proportions and
different thickness in plastering work per 1 sq.m. And how
to estimate this quantities.
Answer Posted / manoj patel
Theoritically;
> for mix Proportion 1:3;
> 12mm thick,
> 1m2 plaster will require 6.20kg of cement.
Assumption - No Wastage
Plaster Yield - 70%
| Is This Answer Correct ? | 19 Yes | 5 No |
Post New Answer View All Answers
Can we apply curing compound on ceiling (slab Bottom)
What in your opinion makes you the most suitably qualified candidate for this post of civil engineering technician?
For what purpose bedding is used under storm water drains?
what's the formula for calculate pcc for matt(45mm aggregate)?
What is meant by dimensioning?
what is the use of water bar in water tank and is this an extra item in estimate?
WHERE CAN I GET THE PREVIOUS QUESTION PAPERS OF APGENCO FOR THE THE POST OF Tr.ASSISTANT ENGINEER(CIVIL)
For elevated service Reservoirs what will be the output of each skilled carpenter and bar bender.
from where ican get sample papers for CET-delhi 2012
what is Quantity of stone and sand required for one cubic meter of stone work (UCR)
For fine aggregate which is most suitable River sand or crusher sand & why ?
What is the amount of work done by a carpenter, bar Bender and plaster Mason in interior and exterior plaster
Maximum cement content in 1cum for RCC and PSC? (please give IS,IRC referance?
how much cement and sand required for 100sqm of wall plastering in different proportions
Define mirror?