what is the formula to find battery back up of ups?

Answer Posted / bala_vlsi

Fomula

Watt/d.c voltage )x 1 / (p.f )x (1/ Efficiency) x Required
Hrs

Example

Data
500 W = load
12 V = d.c vOLTAGE
0.9 = P.F (ASSUMED )
0.8 = mAINTAINANCE fACTOR(ASSUMED )


500 / 12 X (1 / 0.9 ) X (1 / 0.8 )X 2= 115 AH Battery is
need to priovide 2 Hrs back up supply

Is This Answer Correct ?    2 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

why cable i burning without tripping. how can protect led street lights

1034


Rules and standards of electrical control wiring ?

644


Why need 3phase machine double earthing?

1343


What is a parabolic signal?

645


What is Faraday's law

1060






Did RMU have ct and pt ?

953


Why should be the frequency 50 hz 60hz only why not others like 45, 95 56 or anything , why should we maintain the frequency constant if so why it is only 50 hz 60hz?

712


how we can explain arc heatng?

1467


How Calculet The UPS AH In Load

1235


we have two generators different capacity on 15 MW and other 6MW at 11 KV , 15 MW gen. bus short level current 40KA,and 6MW short level current 25KA,, length of cable 100MTR between 6 MW from 15MW gen. for bus coupling . kindly tell any one can we use both NGR OR one NGR from any GEN. BOTH NGR has diff. rating. Tariq pakistan

1232


WHY TERTIARY OF POWER TRANSFORMERS IS LOADED WITH EQUIPMENTS LIKE CT,PT,ISOLATOR AND CB

1469


what will be d.g. capacity to cater together for 14hp A.C. load & 3kw lighting load

1557


how to CHECK CT AND PT AT THE FAULT OCCUR IN GENERATOR RELAY PANEL .

1752


WHAT IS THE WINDING PROCEDURE OF ELECTRICAL MOTOR

3534


hello friend i wish to study a course related to the electrical construction, controlling and monitoring , which course i want to study? pls give me the name of institute?

1348