what do we mean by hook up drawing. what r the information we
get from it?
Answer Posted / bala
Hook up drawing: it's a drawing that details about
1) Installation procedure based on type of fluid & its
parameters like temp, pressure, flow rate
2) Type of material to be used to measure based on fluid &
its parmeters.
3) Scope of work between mechanical & Instrumentation.
4) Bill of materials
| Is This Answer Correct ? | 7 Yes | 1 No |
Post New Answer View All Answers
If a warning lamp will operate with the ground circuit is bypassed with a jumper wire to ground, what should you check?
how to work static pressure sensore how to work dpt
What is the purpose of bypass valve across AS valve.
centrifugal compressor interlock? Tell me the parameter at which compressor will trip
what is the input of digital counter during the the calibration time?
What is the calibration procedure of Drum level transmitter if range is 0 to -400 mmh2o in lab?
How an rtd work, and what volts/current goes to a rtd to measure the resistance?
how to calibrate mass flow meter (Coriolis)? Example calibration range: 0 to 2500 kg/hr line size 3" fluid: Etheline glycol (MEG)
why Fahrenheit unit of moistur analyzer transmitter
I am having a Phoenix digital to modbus converter. The o/p of the same is connected to flow computer FB407. But the digital signals are updated only after one minute in the flow computer. what may be the cause of delay in communication? Flow computer is having a scanning period of less than 1 sec.
What is the use of single seated valve?
What is the difference between ff transmitter and non ff transmitter
How to decrease opening & closing time of on/off valve?
For crude application in floating roof tank, how to calibrate a DP Transmitter? How is the floating roof weight considered?
How will you test a transistor with a multimeter?