how we can calculate the capacity of a proposed canal in a
command area.
Answer Posted / khalil
first of all duty of the command area is determined. Then
we multifly discharege into acres. for example if duty 1
cusec/100 acres the area is 1000 acres then discharge of
the canal is 10 cusecs. if the canal shape is trapezoidal
then we put by hit and trail method varous d and b.
| Is This Answer Correct ? | 8 Yes | 2 No |
Post New Answer View All Answers
What is meant by Crystal Concrete?
What is the difference between a wood shake and wood shingles?
what is moment-curvature relationship in semi rigid connections??
What is meaning of Canceled/Flat Beam. What is difference between them? Both type of beam can bear same load if size (width)of the flat beam is increases and depth is same as slab thickness? Kindly suggest to me.
Sir, Iam Applied in rrb for the posts of Junior Engineer.I want to know about the or question previews to study well.Pl send it to shukla_varun1985@yahoo.com.
We are into industrial flooring (epoxy flooring) business. We buy material from manufacturers.We supply and laying the to companies. In our billing what tax/ taxes to be claimed from companies? Are we applicable for only WCT or any else?
what are the grades of concrete?where and or what purpose a particular grade is used in a particular structure?
How can i display 5 asterisk and another 5 asterisk )?
What is the difference between Grade I, II and III of GSB?
Define What is a projection line?
Give me an example of a time when something you tried to accomplish and failed.
what is the weight of 10mm,20mm,40mm aggregate
Which is the direction of negative angle?
What is meant by autocad?
what is the minimum reinforcement provided in beams,footings,slabs? what is the minimum soil bearing capacity to design a multistorey building