Answer Posted / louis
Production versions is also used when:
- Routings; more than one Production line is used (with
different Costs),
- Alternative BOM's: is used to produce the same Finished
product, Example: in Pharmacutical 2 different chemicals
can be used to manufacture "Disprin's" etc.
*** It is defined in the Material Master & Production
Order.
| Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
Explain variant configuration
What are gaps? Some examples?
What is alternate item group?
Explain Kanban.
How mrp (material requirement planning) types are classified?
Explain schedule margin key
What is MRP group?
Scheduling times can be defined in the material master record by?
What is primary cost and secondary cost?
Have you used Pull list or back flushing in REM?
Different types of consumption based planning.
what are the settings needed for variant configuration?
What happens to planned after it has been converted into production order ?
Both labor and machine categories exist. How would you calculate the process time?
What is detail scheduling