Is there any option to replace two Genset of capacity 125KVA
with one higher capacity for same office?
Answer Posted / william lobo
Looking at your new feedback; it is possible to install a
new DG set of higher capacity. Since the DG sets are on
rental then its more easy. Just ask the DG set supplier (
the one whose performance is satisfactory) to come over and
surely they will be able to give you free advice on how
best the conversion should be done.
The the electrician or engineer who did the job of
providing necessary switchgear and cabling etc for the
additional loads could be contacted and surely he too would
know what best could be done.
But this may entail higher capacity switchgear, cables etc
to be installed in lieu of the existing set up.
Or like the suggestion to provide one 400A TPN and from
here the same original cables could be used to the existing
lower capacity switchgears.
Also one higher capacity new cable is to be installed from
the new DG set to the 400ATPN.
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
any earth foult trip the relay but in welding time not trip by earth foult
How can I calculate per unit (KWH) fuel (Gas/ Diesel both) consumption 1MW unit?
Haw to check conductivity of budbar
What is Fire Panel ? How it works ?
what is the function of impulse relay
what is the difference between c power and U power acb breaker
Is it required to do earthing in 2nd shop if earthed armoured cable is laid from 1st shop ?
Please explain the following and how these are working with PLC unit 1.I/O Module 2.I/O Device 3.Adaptor Card 4.Ribbon Adaptor 5.RS 485-FC
If not into production, how far did you follow the design and why did not you see it into production?
What will happen to the protection and metering, if the polarity of a single or two PT/PTs in three phase system is reversed? Please provide reference if any.
What should be current in the Primary and secondary side of 1000KVA (11KV Supply)Transformer.?
how to failure indution motor insulation & how to improve heat in motor insulation
3 phase Motor will be given 2 phase after 2 to 5 second we given 3rd phase so Motor Run sum-time in forward or sum time run reverse direction. All time phase sequence is not change. Why motor run in reverse direction? Please Explain........
difference between ac series and parallel circuit
formula for calculation of switchgears(i.e. contactor, fuse, cb, relay etc.), if load current is given?