Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

what is Entrance and Exit criteria ?

Answer Posted / ramyab.mca@gmail.com

Hai....

Entrance Criteria:

The Entrance Criteria specified by the system test
controller, should be fulfilled before System Test can
commence. In the event, that any criterion has not been
achieved, the System Test may commence if Business Team and
Test Controller are in full agreement that the risk is
manageable.

* All developed code must be unit tested. Unit and Link
Testing must be completed and signed off by development
team.
* System Test plans must be signed off by Business Analyst
and Test Controller.
* All human resources must be assigned and in place.
* All test hardware and environments must be in place, and
free for System test use.
* The Acceptance Tests must be completed, with a pass rate
of not less than 80%.

Exit Criteria:

The Exit Criteria detailed below must be achieved before
the Phase 1 software can be recommended for promotion to
Operations Acceptance status. Furthermore, I recommend that
there be a minimum 2 days effort Final Integration testing
AFTER the final fix/change has been retested.

* All High Priority errors from System Test must be fixed
and tested
* If any medium or low-priority errors are outstanding -
the implementation risk must be signed off as acceptable by
Business Analyst and Business Expert
* Project Integration Test must be signed off by Test
Controller and Business Analyst.
* Business Acceptance Test must be signed off by Business
Expert.

K,Byeee...
Thanks & Regards
B.Ramyasri

Is This Answer Correct ?    3 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Hi, My name is Dinesh.I want to prepare for ISTQB certification , So can anyone please email me the syllabus of it and what is criteria for giving exam.Please email me answers at: dinesh0323@live.com

5233


what is the difference between section & test feature in test case documention?

2157


Which testing model is best as per your understanding, and why?

1195


how do u manage scripts in winrunner when you application is changing frequently?

1971


How to write test cases for nevigating menus? Ex. Course -Topics -Subtopics

2213


Write the test cases for yahoo home page

2296


How many bugs occured will be considerd appropriate over 1000 steps when inspecting software? Describle an approriate Bug value.

2120


1.what promted you to become involved in QA/Testing?

2246


What is positive and negative testing?

1139


What are the advantages of waterfall model?

1125


Please explain me v-model clearly i want to know how it works and want to know how it use in real time on a project please tell me its urgent and important for me understand .Please tell me my mail id is Chiku_69@yahoo.in Thank u

2629


hai friends i need a general test cases for check box,drop down button and radio butoon can anybody reply me plz..........thanks in advance

2083


wat are the questions would the project leader ask about the project?? please do send the answers early.

7988


What is desk checking and control flow analysis

1339


Wat type of questions ll be asked in interview for an 1-2 yrs. experinced persond and i need some database concept question in testing.

2311