Answer Posted / ramyab.mca@gmail.com
Hai....
Entrance Criteria:
The Entrance Criteria specified by the system test
controller, should be fulfilled before System Test can
commence. In the event, that any criterion has not been
achieved, the System Test may commence if Business Team and
Test Controller are in full agreement that the risk is
manageable.
* All developed code must be unit tested. Unit and Link
Testing must be completed and signed off by development
team.
* System Test plans must be signed off by Business Analyst
and Test Controller.
* All human resources must be assigned and in place.
* All test hardware and environments must be in place, and
free for System test use.
* The Acceptance Tests must be completed, with a pass rate
of not less than 80%.
Exit Criteria:
The Exit Criteria detailed below must be achieved before
the Phase 1 software can be recommended for promotion to
Operations Acceptance status. Furthermore, I recommend that
there be a minimum 2 days effort Final Integration testing
AFTER the final fix/change has been retested.
* All High Priority errors from System Test must be fixed
and tested
* If any medium or low-priority errors are outstanding -
the implementation risk must be signed off as acceptable by
Business Analyst and Business Expert
* Project Integration Test must be signed off by Test
Controller and Business Analyst.
* Business Acceptance Test must be signed off by Business
Expert.
K,Byeee...
Thanks & Regards
B.Ramyasri
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
write test case for linked in sign up page ?
How does a coverage tool work?
how is market for testing in banglore,chennai,pune,delhi?
Why you are selected software testing as career ?
Work flow in testing in your company?
Hi there, I am new to the world of testing. Is there any place where I can have a look at an actual specification documents or test plans or test cases. This will help me in generating a level of confidence. Looking forward to your replies
how to connect oracle with test director? in testdirector we will be getting only reports? pls answer Thanks in Advance
Who are all involved in an inspection meeting?
what are the typical problems in web testing?
Test cases for Internal IP Messenger
how mapp the defect id in quality center?
You have a testing team of 10 members, and now you have to reduce it by 5 member and you dont want to increase risk in your product, you are try to cover all functionality to test. What test Strategy you follow.
What are all the netwoking tools, hardware tools and software tools required for testing a web-based n client server applicatopn?
What is mutation testing & when can it be done?
what is test scenario and test condition?