How many no of bars in a bundle of steel and kgs/bundle. 8
mm, 10mm, 12mm, 16mm, 20mm with both MS and TMT separate.
Answer Posted / us rao
rediculus questionif asked in an interveiw.usually it is 10
to 12 numbers of 12 metres length
Is This Answer Correct ? | 56 Yes | 44 No |
Post New Answer View All Answers
how many sqft or cft of work done by a mason per day in all works such as brick,block,concrete,shuttering carpenter,reinforcement fabricator,painter,door window carpenter.....everything thank you
what is diffrence between catchment area,watershed and basin?
how is the reinforcement is distributed in triangular slab
what is the quantity of block work required to construct a compound wall of 6" thick,and 212 lenght
what is the theoritical percentage of concrete cubes testing per day?
What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.
how to calculate the length diamond shaped striupps in column
What you understand by richter scale?
VAT and CST ? Which benefits for buyer ? Why benefits?
what energized you to complete your course?
With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr
Whats the meanig of ,'K' VALUE in the case of soil.....
Re: Can anybody help me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates? please my email id is smgujjal@gmail.com
03. a. The water cement ratio for achieving maximum strength of concrete is…… 1 b. Water/ cement is inversely proportional to-------------- 1 c. Increasing the slump decreases the strength: True / false 1
primary treatment of sewagw consist of removal of floating materials removal of sand & grit removal of organic materials all above