Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

what"s the formula to find the quantity (consumption) of
cement,sand,aggregate for 1m3(1:2:4)?

Answer Posted / prakash kale

for 1m3 conctre --

Take a 52% added dry surface of concrete

1+.52 = 1.52

i.e.
For 1.52 cu.m. concrete
Then
1.52/1+2+4=1.52/7
=.21714
=.22
so.22/.0354 =6.2 bags(1 bag = .0354 cu.m cement)

6.2 bags/cu.m in 1:2:4
Sand--
.22 x 2 =.44 cu.m.

Is This Answer Correct ?    118 Yes 13 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

calculate the quantity of water for 1:6 cement mortar

2100


What is thumb rule in quantity and cost estimation of a residential building?

3068


What is the procedure of concealed plumbing in toilets?

2292


five requirements of infill panels for walls?

3674


what is the design procedure for building

2232


foundation details for 25 ton weight Furnace on 2 supports and 2 tilters

1503


a sewer which receives the discharge of no. of house sewer is called house sewer lateral sewer intrcepting sewer sub-main sewer

2511


Can we use Polystyrene as a Bitumen modifier !! if so is it a good MS research topic ? and what type of laboratory tests will be conducted during Research work ??

2205


What is eccentricity in laymans term Can't understand bookish language .please explain in easy way.

2410


What are the advantages and disadvantages of lead products in construction?

1139


In foundation design, while we do the base pressure check, we normally check if the attained pressure value is less than the GROSS BEARING CAPACITY of the soil which is the sum of net bearing capacity of soil and the overburden pressure. Actually, the overburden pressure acts against the net bearing capacity of the soil and I feel that we are actually increasing the bearing capacity value and doing the check. I feel that this is NOT right. Please clarify on this.

2212


pls tell estimate for 1 kilometre length random rubble masonry 0.90 metre height 0.600 metre width

1525


Types of column foundation and how to calculate its steel quantity.

1892


How many cement sand ballast in cc 1:4:8 40mm

1947


do we consider shrinkage factor for calculating cement consumption for CM mixes for different works?

1685