Design steps of one way slab
1. Depth of slab
d= lx/20 * M.F. (M.F. = Modification factor)
Assume the dia. of bar (8, 10, 12) and
Final overall depth
D= d+15+0/2
d= d-15-0/2
2. Effective Span
This is taken as the lesser of the followings
a) Center to center distance between followings
L= lx + t
L= lx + d
3. Load
Consider 1m width of the slab and find out the total udl
a) W = (Self weight + Live Load + Floor finish)
b) Find factor load
Wu = 1.5 * w
4. Factor bending moment
Mu = Wu * l²/8
5. Equating Mu limit to Mu find the depth req. if it is
less than‘d’ than O.K otherwise
Increase D & repeat 2, 3, and 4
Mulimit = Mu
6. Area of main steel
Pt = 50fck/fy (1-√1 – 4.6 Mu / fck bd²)
Ast = Pt/100 *100* d
7. Spacing of main steel
S = Area one bar * 1000/ Ast
Check: - a) 3d
b) 450 mm
8. Distribution Steel
Astd = 0.15 % of Ag -Fe 250 (mild)
= 0.12% of Ag – Fe 415/5000 (torque)
Ag = b.D
9. Spacing of distribution steel
S= Area one bar * 1000/ Astd
Check: - a) 5d
b) 450 mm
10. Check for depth
a) Žv = V/bd
b) Pt —› Zc
c) Zv < Zc …….. No shear reinforcement req.
Is This Answer Correct ? | 146 Yes | 35 No |
Post New Answer View All Answers
Explain different types of rcc pipes.
How does siphoning work?
How cracks in concrete can be avoided?
what radial pressure, the NP2 class rcc pipe can sustain?
I used Etabs software to analyse a high-rise building. And I want to use templated UBC-codes inside to calculate the Seismic load. My question is: whether or not I have to control the seismic load by base shear load which is manual calculation? (just for more clarification: I can control this by input the scale factor into Eartquake definition in Etabs) I would highly appreciate your answer.
Find out Cutting Length of Steel for Right angle Triangle? Where Opposite Side 4m, Adjacent side 6m. (Assume cover 40mm)
For plate load test why we are applying pressure 3 times the proposed allowable bearing pressure? Is there any supporting standards for this?
what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?
1m square 20mm plastering how much of water need curing work
How to estabilish reinforcement Steel rolling margin for a building projects ?
What are the basic use of runners and standards of pipelines?
What are the benefits of rcc pipes over steel designed pipes?
How do you compute volume of airflow?
which red: used in roof teping, then use only cement
what is kribs is supporting?