how to calculate the required qantities of cement, Sand and
aggrigate to prepare 1 Cum of concrete mix 1:2:4
Answer Posted / er.puspak kumar sahu
concrete ratio=1:2:4
area=1cum
1+52%=1.52cum(add the extra 52% for dry material)
cement=1.52/(1+2+4)=0.217cum=(0.217/0.035)=6.2bags
(per bag cement volume=0.035cum)
sand=1.52/2=0.76cum=(0.76/0.028)=27.14cft
(0.028 is a conversion factor)
aggrigate=1.52/4=0.38cum=(0.38/0.028)=13.57cft
(0.028 is a conversion factor)
finaly=
cement use in per 1 cum=6.2bags
sand use in per 1 cum=27.14cft
aggrigate use in per 1 cum=13.57cft
| Is This Answer Correct ? | 4 Yes | 11 No |
Post New Answer View All Answers
by which materials we can prepare circular shuttering with tentative cost of material(rate analysis)
How to come 1.54 from dry to wet concrete?
pls tell estimate for 1 kilometre length random rubble masonry 0.90 metre height 0.600 metre width
plumbing CPVC fitting FTE Brass full form
For 1 bag cement how i will calculate sand and metal aggregate;Here the mix proportion is 1:2.49:2.38
how to calculate labour strength for work for RCC,brickwork,blockwork,in &out plaster,flooring,dado,door frame & shutter,painting etc for constructing highrise building?
In case if concrete box girder bridges how is the number of cells determined?
Please tell me any one, how many quantity concrete paver block fixing perday ( 8hours) per mason??
Please tell me vasthu room sizes. Thanks.
How much cement will require for 1Rmt Skirting laying
What is the quantity of cement used for stone pitching work of 100sqm 225mm thick and cement mortar of 1:6? And how?
it is a corrected question." make a list of engineering property(properties) of soil.
can u plz send me ntpc placement papers(civil engineering) at mohit_verma21@yahoo.com
rimmer in pile foundation
Define What does civil status mean?