Answer Posted / brijesh
Primary current injection test require at the time of
commissioning to the current transformer.
The purpose of it is to check the ratio of C.T.
and for checking of C.T. circuit.
The test is conduct by means of primary injection test set.
In test set there is a current transformer and variac.
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
700KW 6.6KV slip ring induction motor to use VFD to control the speed
in dc suppy frequency is zero why? if dc frequency is zero how to exist dc transients and ac transients
how to produsing geretor power
If UG power cable both ends are to be earthed or what? If not why?
plz explain the auot-reclosing circuit in electrical engineeing
An automatic water heater is an example of which type of control system?
What is the tests required for a 132 kV, 400 kV , 765 kV for a Circuit Breaker and Power Transformer before commissioning ?
i want use the cable size 16cx4 core aluminium usege watts 240x2000w this cable size is correct?
I am shobana from Chennai. I am having my personal interview on 19th Dec at Chennai.kindly mail me the questions to mail id shobana.shanthi@gmail.com
mostly the questions were from machines... d.c. machines, transformer, synchronous and induction all theory paper........ few from power system... but the level of paper was easy.....
How much costly in percentage wise is sandwich busduct costly than air insulated busduct of any rating?
wht is embedded systems? what is new inthis field?
compare between starting charactristics of synchronous motor with those of 3Q Squirrel cage induction motor
give me atleast four differences between circuit and network
advantage and disadvantage of team work?