when a primary current injection test is required, it is
accomplished by what?
Answer Posted / brijesh
Primary current injection test require at the time of
commissioning to the current transformer.
The purpose of it is to check the ratio of C.T.
and for checking of C.T. circuit.
The test is conduct by means of primary injection test set.
In test set there is a current transformer and variac.
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
How to calculate the External Resistance required for 60HP slipring motor in case no any data of the Motor is available???
does buccholz in a transformer use batteries
Explain RLC circuit?
What is the complete procedure of erection of electrical panel in industry
5- What is the task (function) of the excitation and isolation transformers in power plant? 6- What is the task (function) of LCI (A), LCI (B) and LCI (COS) in power plant? : LCI (A) and LCI(B) are load commutating inverter for generator turbine starting. , LCI (COS) is load commutating inverter change over switch
What are the necessary solutions needed to be carried out on a malfunctioned earthing mechanism of a VACUUM CIRCUIT BREAKER.(TAMCO)
i ha done my 10th with 71% ,ITI with 81% 11th with 75% 12th 43% apprentiship with 71% in SAT i secure 1390 ,TOEFL 27 i was refused four times and in all me interview visa officar told that i am not Qualify for study in USA but i completed my 12th yes i got low persentage in my 12th but i seen to much student they already got visa with them 3 or 4 backlocs so why they are refused me ?
How grounding is different than earthings?
Pl.brief me any electrical major fault you have rectified.
What is the types of HT motor testing
Difference between RCCB, RCBO and ELMCB.
how to check avr of dg set of 125kva
please send me the previous year's question papers of jindal GET exams
HOW DO YOU CAN CHECK A 15KV DIODE, WHETHER IT IS OK OR NOT?
Hello sir i m student of gtu .what is idp.