What is eXtreme methodolgy ?

Answer Posted / srinivas

IT is one of the Agile methodologies for SW development .
Follows 12 core practices , one of them is pair programming.

Is This Answer Correct ?    3 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How do you ensure that your project is always on track?

663


You are a project manager working for Mail House King. Your company processes orders for several mail-order catalog companies. Your project is to install new mail-sorting equipment and software. You’ve had some problems and experienced some variances so far during the project. Your project sponsor has asked for an EAC. You know the following information: PV = 800, BAC = 700, EV = 675, AC = 750, and ETC = 30. Which of the following is the correct EAC given the circumstances? A. 778 B. 780 C. 861 D. 833

945


The purpose of a quality audit includes all of the following except: A. Examines the work of the project and formally accepts the work results B. Determines how the project is progressing and makes corrections C. Identifies lessons learned D. Reviews quality management activities to ensure the right quality elements are being examined

941


You are the project manager for a new website for the local zoo. You need to perform Qualitative Risk Analysis. When you've completed this process, you'll produce all of the following outputs except: A. Overall risk ranking for the project B. List of prioritized risks C. Inputs to other processes D. List of risks for additional analysis and management

883


You are a project manager with several years of experience in project management. You’ve just accepted your first project in a foreign country. You've been in the country a week or two and are experiencing some disoriented feelings. This is known as: A. Collocation B. Diversity shock C. Global culturing D. Culture shock

691






You work for a large manufacturing plant. You're working on a new project for an overseas product release. This is the company's first experience in the overseas market, and they hope to make a big splash with the introduction of this product. The project entails producing your product in a concentrated formula and packaging it in smaller containers than the U.S. product uses. A new machine is needed in order to mix the first set of ingredients in the concentrated formula. Which of the following is true? A. The new machine, the concentrated formula, and the smaller package are each project constraints. B. The new machine, the concentrated formula, and the smaller package description must be incorporated into the product description document. C. The new machine, the concentrated formula, and the smaller package are each project assumptions. D. The new machine, the concentrated formula, and the smaller package are each considered deliverables.

895


Your project depends on a key deliverable from a vendor you've used several times before with great success. You're counting on the delivery to arrive on June 1. This is an example of : A. Constraint B. Objective C. Assumption D. Goal

1137


You have collected the performance measurement documentation for your project to be included in the project archives. What is the purpose of the performance measurement documentation? A. It's used as part of the formal acceptance process to verify contract expenditures. B. It's reviewed to make certain the project goals and objectives were met. C. It's included in the project archive documentation after confirming the accuracy of the measurements. D. It’s used as historical information for future project that are similar in scope to this project.

821


Ruby is an administrative assistant with another department. Her manager has agreed to loan Ruby's services to you on a part-time basis during your current project. Ruby is putting together the cost projections you've gathered so far. You want to include these costs in the project charter. Ruby is formatting this information for you into a spreadsheet package and is printing copies. Which of the following is true? A. All of the costs, including Ruby's time, are charged to the project. B. All of the costs, Ruby is typing into the spreadsheet are project costs. Ruby's time is not directly related to the project and should not be included. C. The project costs, including Ruby's time, should be included in the project charter. D. The project costs, excluding Ruby's time, should be considered project constraints.

746


You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any rime during the day. The project sponsor has promised you a bonus if you get this project completed two weeks sooner than the scheduled project end date. The bonus will come in handy on your trip to the Bahamas planned for later this spring. You've got a few remaining project activities to wrap up before you can close out the project. Which of the following is the most appropriate response? A. You tell the sponsor the project is complete and treat the remaining activities as though they're problems that came up after project closure so that you can still get the bonus. B. You tell the sponsor the remaining activities are outside the scope of the project so the project really is completed and collect your bonus. C. You tell the sponsor the stakeholders added these requirements after the project was well under way and you never agreed to include them in the project so the project really is complete, and you collect your bonus. D. You tell the sponsor you aren't going to make the two-week early completion date as there are remaining activities to finish up.

782


You are the project manager for BB Tops, a nationwide toy store chain. You are working on estimates for your latest project and have gathered several variables for your model. You've determined the following: A. Parametric modeling is a top-down technique that uses variables to produce time estimates. B. Parametric modeling is a mathematical formula that uses variables to produce cost estimates. C. Contingency estimating is a top-down technique that uses variables to produce cost estimates. D. Contingency estimating is a mathematical model that uses variables to produce time estimates.

695


What is the triple constraint triangle in project management?

718


You are a project manager with technical expertise in the pharmaceutical industry. You've decided to try your hand at project management in the entertainment industry. Which of the following is true? A. You will likely be successful because communication skills are your strong suit. You anticipate having technical experts on your project team to address industry specifics that you're not familiar with. B. You will likely be successful because your organizational skills are excellent. You anticipate having technical experts on your project team to address industry specifics that you're not familiar with. C. You will probably be successful because you have a friend in the entertainment industry that has briefed you on all the important aspects of this project that you'll need to know. You anticipate having technical experts on your project team to address industry specifics that you're not familiar with. D. You will probably not be successful because you have little knowledge of the entertainment industry even though you anticipate having technical experts on your project team to address industry specifics that you're not familiar with.

765


What are the tools and techniques of the Contract Administration process? A. Contract change control system, payment system, payment requests B. Contract change control system, contract negotiations, payment system C. Contract change control system, contract negotiations, contract changes D. Contract change control system, performance reporting, payment system

682


How do you manage team performance?

648