Answer Posted / smita rao
After finalizing of possible test for current project ,test
lead category people concentrate on test plan
document .Preparation to define work allocation in terms of
what,who,when and how to test.To prepare test plan
document ,test plan order follows an approach:
1.Team formation :-
a) Availiability of testors
b) Test duration
c) Availiability of test environment resources.
2. Identify tactical risks :-
a) Lackf knowledge of test engineers on the domain
b) Lack of resources
c) Lack of budget
d) Lack of test data
e) Lack of communication between test engineer and
development team.
f)Delay of modified build delivery.
3.Preparation of test plan:-
a) Test plan id
b) Introduction
c) Test Items such as modules ,functions,services
d) Features to be tested
e) Features not to be tested.
4.Review test plan :-
a) BRS and SRS coverage
b) TRM based coverage
c) Risk based coverage.
Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
I want to do certification in ISTQB please anybody hepl me with the details and site to refer for further details.............if possible give me the material as well on my mail id a.vishwakarma@aol.com. Please help me........Thanks
What's the relationship between environment reality and test phases?
Write all combinations of test cases for calculater on + symbel
Explain Single View Testing ?
What is big bang approach?
Can any tell me how a clinical data management system is tested? what are the test scenarios? what are the test cases? work flow.
What is concurrent user hits in load testing?
Hi Friends, I want to know the best institute in hyderabad which is giving training in 'SAP Testing' and who is the best faculty. Regards, Imtiyaz..
1) Test summary contains ? 2) Requirement Tracebility means ? 3) Test Effort contains ? 4) Test Planning Productivity ? 5) Metrics should be caluclated ? 6) Interest rate Rsik is a type ? 7) Test analysis and Design process task? 8) secured loan is a part of Liability (or) assest in a balance sheet? 9) Money Market means? 10) a ------ specifies all of the terms of a loan and the obligations borrower ? 11) what is a primary market is ? 12) Quality of Testing measure with ? 13) Company has a share with facevalue 10 rs/- and NAV of 37 after comapny has given Dividend of 35 % then How much NAV become ? ( I don't know what is NAV means, question overall Idea I am giving not 100% perfect ) the potions for these are 1) 33 2) 33.50 3) 37 4) 42 14) one compay has taken 10 million loan from a bank for a Interest rate is 10 % and base amount is 0.4% so how much they had paid monthly Emi ? they provideansews like 1) 100000 2) 114000 3) 140000 4) 104000 Remaing questions I not remember.
how do u manage scripts in winrunner when you application is changing frequently?
is it possible web application make it as executable file
aplitue questions will be based on wich type ?
What is bottom-up approach?
hi every one can you send me ISTQB Course material on my Email id deeptimundra997@gmail.com
What are the cases when you’ll consider to choose automated testing over manual testing?