Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

In case of a beam ,main steel is provided along the longer
span because, bending moment is directly proportional to
length but why in case of one way slab main steel is
provided along shorter span while as bending takes place
along longer span?comment

Answer Posted / naresh

For beam: Depth is more than width so we provide main bars
in longer span
For slab : Depth is lesser than width so we provide main
bars in shorter span

Is This Answer Correct ?    3 Yes 4 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is the name of this multiplication factors ?

2131


For plate load test why we are applying pressure 3 times the proposed allowable bearing pressure? Is there any supporting standards for this?

1803


Questions related to civil.engg in company

2029


Can inverted beams used in pipes during construction?

1330


how do you calculate the quantity of steel,cement for plinth beam. (example size 41'*0.58'*1.08')

2637


What is the Hardness of M-40 grade concrete, general and theoratical

2117


how much used soil in 1 brick of standard size?

2068


what is c4x light weight cement blocks

5657


how to identify the failure of building by expansive soils

1650


How do you maintain water pressure?

1182


Steel requirement in kg of 6" thk slab Total qty 32.64 m3 Beam / column qty 35.39 m3

2086


what will be the total emoluments for deputy surveyor in APPSC in the payband of ( 9460-27600). please give me the detailed information step wise?

2289


What are the RISKS during the project construction?

2283


whou haat goals do you have in your career

2150


how meny typs of renging rod?

2268