calculation of cement bags in 1:2:4 concrete mix
Answer Posted / akashkhutia
For 1 m3 of concrete (1:2:4)
Required volume of concrete = 1 m3
Estimated volume of dry material = 1 x 1.65 = 1.65 m3
Mix totals = 1+2+4 = 7 (1:2:4 cement:sand:gravel)
Ingredient Volumes: 1.65 x 1/7 = 0.235 m3 cement
# Bags of cement: 0.235 m3 cement / .0332 m3 per 50 Kg bag
= 7 bags of cement
| Is This Answer Correct ? | 216 Yes | 82 No |
Post New Answer View All Answers
how many digree of freedom in four bar chain
how to prepare site mix design
1. 1. The mass of a chunk of moist soil is 34 Kg and its volume is 0.012 cu. Meter. After drying in an oven, the mass reduces to 14.25 Kg. Determine the water content, the density of moist soil, the dry density, void ratio, porosity and degree of saturation. Take G = 3.25
sir when can we expect the AEE results and when will be the interviews sheduled please guide us in this regard thanking you
in a corner footing of a building, column lies in one corner. in this condition i want to know if the reactive pressure of soil will be uniformly distributed throughout the footing or will be uniformly varying as in the case of eccentrical loading.
quantity of sand and cement for 10m2 plastering 10mm thick for the ratio of 1:4,1:3and its leabour data
reinforcement slab, beam and column formulas?
can you mail me detailed procedure,entire syllabus and practice papers of mpsc civil engineering branch.I am in third year now
How to marking the building
how to do cementicious paint for rcc walls of cw pump house
You have 3 snd sample of different FM=0.21,FM=0.95,FM=2.90 which one is suitable for a)plastering on R.C.C b)plastering on masonary wall c)concreting column d)concreting of bored pile.also justify your answer.
How should we design a brick column and footing?(note: no reiforcement to be provided) Can you tell me any reference book where i could possibly find this design? Plz help urgently
can any one explain bar bending schedule of bems and columns and slabs ??
construction workers how much time take one work or qty
Can anyone suggest how to determine scheduling of reinforcement of floor beams from Staad model,other than clicking each beam respectively 7 noting down the values ?