Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how to calculate quantities of sand , cement & aggregate in
1m3 - M20 , 1m2 of 6mm/12mm/20mm plaster , 1m3 20cm/ 1m2 of
10cm brick wall, paint quantity for 1m2 snowcem and lime
painting?

Answer Posted / sjtbehera

1. Grade of concrete M20 so ratio is 1:11/2:3
let volume of concrete - 1cum
total ratio- 1+1.5+3 = 5.5
cement = 1x15.4/5.5 = 2.8 cum so cement is =2.8/.347=8 bags
sand-2.8*1.5= 4.2cum
aggregate- 2.8*3= 8.4 cum

2. plaster = suppose 12mm palster
consider 1 sqm ratio is 1:6
volume of concrete= .012x1= .012cum ( per 1sqm)
incrase 20% for joint, filling and wastage=.012*20%=.0144

calculate 1/3rd of mortar when
dry= .0144*1/3+.0144= .0192cum

summation of ratio=7 so cement= .0192/7=.00274cum
= .0789bags
sand= .00274*6=.0164cum

this formula applied for 6mm and 20mm also.
plaster area= paint area

Is This Answer Correct ?    57 Yes 49 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

how much one carpenter can doing shuttering of slab in one day

3328


How to calculate Acctually Brickwork Quantity in Honey Comb Brick in circular Soak Pit

6504


what is smart building materials?

2033


How do you calculate the power of a centrifugal pump?

1149


A doubly reinforced concrete beam is 25 cm wide and 50cm deep to the centre of tension reinforcement. The centre of compression is steel is 5cm from the compression edge. The areas of the compression and the tension steel are 10.16cm2 and 12.56 cm2 if m=18 and the bending moment at the section is 7,000,000 N-cm. Calculate the stress in concrete and steel.

2167


how to estimate costing from quantity givin in BOQ and according to this how we fill tender and final rate for perticular work.....?

2066


What is the amount of work done by a carpenter, bar Bender and plaster Mason in interior and exterior plaster

2299


what is the difference between natural draught cooling tower and induced draught cooling tower

2269


How to arrive the co- efficient of all civil activities? For ex:- painting-enamel in wooden doors. co efficient is 1.8. How this is calculated

2153


how to compute slab reinforcements on step by step procedures??

5740


What are the advantages of cad software?

1116


What are the different types of civil engineering?

1150


What are the points to be considered for calculating cement reconciliation. a)Do we need to deduct the wt of cement bags b)Do we need to adjust the qty due to wt loss during transportation, loading unloading etc or else each bag can be considered as 50 kg bag c)What is the proportion of mix cover block making.

2148


What is meant by dimensioning?

1112


Define polar co ordinates.

1214