how to calculate quantities of sand , cement & aggregate in
1m3 - M20 , 1m2 of 6mm/12mm/20mm plaster , 1m3 20cm/ 1m2 of
10cm brick wall, paint quantity for 1m2 snowcem and lime
painting?
Answer Posted / sjtbehera
1. Grade of concrete M20 so ratio is 1:11/2:3
let volume of concrete - 1cum
total ratio- 1+1.5+3 = 5.5
cement = 1x15.4/5.5 = 2.8 cum so cement is =2.8/.347=8 bags
sand-2.8*1.5= 4.2cum
aggregate- 2.8*3= 8.4 cum
2. plaster = suppose 12mm palster
consider 1 sqm ratio is 1:6
volume of concrete= .012x1= .012cum ( per 1sqm)
incrase 20% for joint, filling and wastage=.012*20%=.0144
calculate 1/3rd of mortar when
dry= .0144*1/3+.0144= .0192cum
summation of ratio=7 so cement= .0192/7=.00274cum
= .0789bags
sand= .00274*6=.0164cum
this formula applied for 6mm and 20mm also.
plaster area= paint area
| Is This Answer Correct ? | 57 Yes | 49 No |
Post New Answer View All Answers
Providing ,Cutting, bending and positioning of TMT Bar with cost of binding wire
what are the five benefits of using standard terminology in the measurement process?
if mineral admixture add into concrete then what is the differences between full cement concrete & fly ash added concrete of their SP. Gr.?and for the changes of SP. Gr. what is the changes in concrete
Give me an example of a time when something you tried to accomplish and failed.
I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work.
give me the rate analysis for Bituminous Macadam and SDBC
please, what is the required bar for a column of 6mx6m the dept is 405mmx300mm,its an axially loaded ?
how much quantity of cement,sand and water required for 1 sq feet flooring work .
a concrete mix 1 2 4 by volume with water cement ratio as .6 by weight if moisture content in F.A is 6% with 20% BULKING AND IN C.A 1.5% by volume. find quantities of different materials required for one bag of cement
Explain the latest method to detect a crack in a building?
What is the bowing depth after stressing of PSC Girder of various spans and various dia of strands?
How to find permissible diagonal tensile stress in reinforced brick work
how many men days of loburs and masons are requirete for 1 cum,pcc (1:2:4),Pcc(1:3:6) and Pcc(1:4:8) thanking you
Explain what is alternate bid?
What happens to Load at yielding ?