what"s the formula to find the quantity (consumption) of
cement,sand,aggregate for 1m3(1:2:4)?
Answer Posted / guest
+1440/(1+2+4)=205 kg in cement
205*2=411 kgs
205*4=822 kgs
or
1/7 = 0.14 cum in cment
2/7 = 0.28 cum in sand
4/7 = 0.56 cum in meatal
| Is This Answer Correct ? | 28 Yes | 34 No |
Post New Answer View All Answers
What is the value of live load that should be incorporated in design of locker room and cash vault room while designing a building for commercial bank?
How to calculate 1 brss for RCC work
resins are not soluble in water soluble in spirit used in varnish left behind on evoporation of oil
1. What is coefficient use for calculation of shuttering. 2. What is coefficient use for calculation of reinforcement in one cum of concrete.
What is costing in 100squre feet bricks
Explain the term 'Gross unit rate' and identify the items that may be included in the gross unit rate.
how much need sand and cement for 1 cft roof construction?
What are the advantages and disadvantages of using plastic and timber fenders?
Q 1) 1 Mason and 2 LABOUR / _________CUM brick work Q 2) 1 Mason and 1 LABOUR / _________SQ FT Plaster work Q 3) 1 Carpenter & 2 Labour/_________SQ FT shuttering work Q 4) 100 SQ FT roof slab concreting ____________mason and labour required
What is the difference between 53 grade and 43 grade cement
How to arrive the co- efficient of all civil activities? For ex:- painting-enamel in wooden doors. co efficient is 1.8. How this is calculated
At one time what is the height of Lift for concreting for Bridge Piers Class B Loading and refer the code.
the volume of cement req for 70cum of brickwork in 1:6 cement mortar is approx is equal to 3cum 5cum 7cum 1ocum
importance of the soundness test to determine the quality of cement use for any construction
i have applied 40mm spacer in the concrete for tie beam. is it correct? kindly give me if there any code available