Answer Posted / girish
Sundhu is exacly right .
It is as per SAP education Book provided.
Pegged Requirement function provide the facility to find out,
Which requirements(like sales order or PIR) have caused to generate which procurement proposal(like planned order or Purchase req. or purch. order ). and It finds the link between the that requirement and its respective procurement proposal.
| Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
Explain 'mrp' (material requirements planning)?
How to create PRT master record?
What do we do in the realization phase?
What is Individual and collective requirements and differecne between them in MTO scenario?
What does the use of ms70 followed by mcec get you?
What is requirement class and requirement type?
How mrp (material requirement planning) types are classified?
What is planning horizon?
What are all the 'sub-components' of production orders?
Two or three Production Orders are there for the same day, and goods are not sufficient and then how to proceed?
How to attach a drawing for a material to bom ? Is it possible ?
What is Production scheduling Profile and use of it?
What is end user training
What is MTS and MTO and the difference between them?
What are the key fields in MRP views?