what is the difference of 53 & 43 grade cement ? expailn
Answer Posted / deepthi ramachandran
The grade 43 and 53 in cement mainly corresponds to the
average compressive strength attained after 28 days ( 6724
hours) in mega pascals (Mpa) of at least three mortar cubes
( area of face 50 cm squared) composed of one part cement, 3
parts of standard sand( conforming to IS 650:1966) by mass
and P/4 (P is the percentage of water required to produce a
paste of standard consistency as per IS standard) + 3
percentage ( of combined mass of cement plus sand) of water
, prepared, stored and tested in the manner described in
methods of physical test for hydraulic cement.
721 hr not less than 23 MPa for 43 grade, 27 MPa for 53 grade
1682 hrs not less than 33MPa for 43 grade, 37MPa for 53 grade
6724 hrs not less than 43MPa for 43 grade, 53 MPa for 53 grade
| Is This Answer Correct ? | 58 Yes | 7 No |
Post New Answer View All Answers
Can anybody help by describing each and every step in short, used while giving a building layout by total station? Regards
Describe a time when you anticipated potential problems and developed Preventive measures
how to calculate weight of 1.8 cum of aggregate
What are the uses of layer?
what are the challenges of being a team leader and a supervisor?
what is derating factor in cable? what does it mean if derating factor is high/low in terms of thermal resistivity of soil?
What is limit state method and working stress method and ultimate method
Prepare a Schedule for a Highrised building from starting stage to Handover?
How is the strength of cement measured?
how to calculate mivan shuttering matrial
I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
Civil engineering material testing Standard results
What is the difference between Hinged and pinned in Column ends
primary treatment of sewagw consist of removal of floating materials removal of sand & grit removal of organic materials all above
Why reinforcement done in shorter span in two way slabs