how to calculate the steel for rcc slab?
plz tell me the formula for calculating the steel?

Answer Posted / vinesh

Ast=(0.5Fck/Fy) into(1-(in sqrt(1-((4.6Mu)/Fck.bd^2))into bd
Fck=grade of cement i.e M25, M20
Fy=grade of steel i.e.Fe415,Fe250
Mu=moment
b=width
d=depth

Is This Answer Correct ?    139 Yes 36 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

why top layer of block work shoud be full size if any cut block adjustable than another layer?

1675


Which code is used for tor & tmt steel bar?

758


at what pressure ply-wood is obtained by gluing wooden sheets

2101


what is the relation between pitch of steel and depth of slab?

2908


What are the responsibilities of a site manager?

628






How to convert 20 dia bar to 16 dia bar in beam without reducing the steel weight

1440


if we know load bearing capacity of the soil and building load falling in each footing, then how to choose the type of foundation??? and if it is shallow foundation then which type of shallow foundation should be choosen i.e either strip or isolated or raft or combined or cantilever footing???????

1815


how calculate the bearing from two coordinates?

1767


how to Concrete cubes testing curing time 7 days casting date 24.05.17 testing date ?

1535


What is chemical composion test

1511


How many days should curing of plastering, brick work and concrete

1211


For making a new road in a village having a school & hospital , tell the steps of construction systemically ?

1166


rimmer in pile foundation

2138


types of piles detail,

1821


what is shuttering co efficient?

1304