In footing (mat) if two different dia of rods are to be used
which rod should be placed at top and bottom ( eg. 10mm &
16mm dia rods)

Answer Posted / ramesh k

Always bigger dia should be laid at bottom and it should be
provided on shorter directions.but for cantilever beams and
sunshade bigger dia should be laid at top,the reason is the
mat shold be laid at top.

Is This Answer Correct ?    11 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How to determine thee cut length for steel reinforcement bars in R.C.C design

1075


what are the proper pipes for salt water line

1872


2nd and 4rt angle elevation used in which country ?

1851


If specific gravity of cement is less than 3.15 what is the cause?

1882


What is the release of lien?

705






how ratio is calculated for any grade of concrete. for e.g. sppose M20 requires(x;y:z) quantity of cememt sand and aggregate.

1577


why do we provide haunches in rcc box or underpasses?

2490


How many Rod required for 58 feet by 24 feet roof slab which is supported by 5 * 3 = 15 Column. Six Stored building Roof Slab = ? Ton 15 Column = ? Ton Slab Beam = ? Ton

1706


How to improve the strength of fly ash bricks to avoid corner damge? How to get the color lighter similar to normal concrete blocks/

1369


Define What is the meaning of a blue land surveyors flag?

776


how many material required for brickbat water proofing of toilets.

1607


Describe about the Pile test methods, which are used in Industrial & Multistory Buildings in general.

1626


2. In a container filled with each of the following materials, at a porosity of 40%, determine the upward gradient required to cause the quick condition (a) Lead shot with a G = 13.75; (b) Fibre beads with G = 2.15; (c) Sand with a G = 2.32

1910


how much shouid be the rate for ready mix concrete per cubic meter

1473


from one meter cube of stone masonry structure how much cubic meter of cement mortar we use as our estimation 25-30% is that correct for estimation of quantity of sand and cement(2:1) proportion of mortar

4166