Answer Posted / vishaljadhav001
When supply side C.B. switched,at receiving end voltage
will not appear immediately."Wavefront" is formed.At left
of wavefront Vtg & current occurs,but at right vtg &
charging current is zero.
This wavefront travels from left to right with wave velocity
(v) which depend upon how fast inductance,capacitance reach
max.current & current .At no load capacitor charge through
inductance step by step.When line charged Vr=2Vs.When load
is connected this capacitor discharged,so vtg appear at
load.so that ferrenti not occurs at full load.
| Is This Answer Correct ? | 3 Yes | 9 No |
Post New Answer View All Answers
Hi Everyone ! My Name is Hakim ullah khan please i need formula of Cable Rating because i want to calculate by self without check any Table Chart... Thank you.....
Why does the speed regulating system adopting I controller have no steady-state error? In this single closed-loop speed regulating system, when the input of the I controller Un=0, what is the output voltage of the regulator? What factors do the output voltage depend on?
What Is Sampling?
Show Details FROM:Muhammed Ikram TO:qa@allinterview.com Message flagged Saturday, June 4, 2011 10:07 PMMessage bodyHello all, i want to ask a question to all of you that what is VMM (voltage monitoring module )? how it work,s? i heard somewhere that it compare 1 phase voltage to other phase voltage. but there is also some setting on it. how to set it,s setting. please tell me briefly. Thank,s and Regard,s. Muhammed Ikram.
what types of cable used in underground coal mining?
What should be the protection scheme for a 15kw, 3-phase motor working in a lathe machine.
Explain about p.t?
How Can You Relate Power Engineering With Electrical Engineering?
While testing LA mast,What are the parameter limits ?
How to measure the Harmonic Distortion of UPS ie THD?
Differentiate between ideal and non ideal current sources?
What are unstable systems?
What happen when change order of CT in GIS feeder?
How the setting of the vector surge relay shall be calculated when the relay is to be used for Grid islanding application?
How generating electric power export to grid from the generating station ?