first wt is reqd. for making a mix design of concrete & the
procedure of determining the qty. of material used in
concrete.
Answer Posted / nravindran
1.Find the Exposer condition
2.Find the grade of concrete
3.What is the minimum cement content
4.What is the maximum water cement ratio
5.Take the standard deviation
6.Find the specific garvity of bulk materials
7.If Admixture required what kind of admixture required
8.Finally adopt the formula
V=[W+C/Sc+1/PxFa/SFa]x1/1000 This is for calculate Fine
aggregate content
V=[W+C/Sc+1/1-PxCa/Sca]x1/1000 This is for calculate Coarse
aggregate
For further details pl refer IS 10262,456
| Is This Answer Correct ? | 4 Yes | 0 No |
Post New Answer View All Answers
What happens when water mixed with cowdung is used for priming instead of water for lifting water in pumps?
In the design of bridge arguments what considerations should be made to select the orientation of the wing walls?
How to design 12*12*14 room having rrc slab ,coloum, beam,foundation?
how much cement sand n bricks required in im3?and how much in plaster?
04. a. Slenderness ratio…………… 1 b. If the height of a stage is 15-0 & dia. of the prop is 5, the slenderness ratio is….… 1 c. If the height of a stage is 10-0 & dia of prop is 3, the number of bracing will be…… 1
pile load testing procedure
Which are the top apps for you civil engineer?
why the openings of sieves are square io size?
Plasterers do how many sqm with spray plaster machine? By hand one mason does 10m2/day. How much they do in Dubai with spray plaster machines?
Mention what are the composition of a landfill?
States some of the commonly used commands in cad software’s?
What is a projection line?
what is Brest Wall?
What are the RISKS during the project construction?
I would like to get the formula How can i calculate the productivity of a mason in terms of brick laying and plaster. i have 6000 Sqmt of interlock laying work i want to calculate - how many masons required to do the job - in how many days can it be done - what will be the production rate in 8 hours shift/ per mason if i can get some excell sheet , it will really help me in my calculations