While testing the 33KV Busbar by using Hipot kit, what
should be the test
voltage we have to apply?
Answer Posted / prabhas
You should apply the voltage step by step till the double
voltage capacity of the cable. this is during only in the
1st time of test for 2nd time onwards 1.8% is preferble.
Ex:33KV: You apply till 65KV
| Is This Answer Correct ? | 4 Yes | 0 No |
Post New Answer View All Answers
In india, according to trade theory above 5 HP motor reqired star delta starter. But we R connect 11 KV motor with 14MW in Direct to line ( With VCB starter combination) Can U Guess, How it is possible ?????
PLZ SEND ME SOME UNIQUE PROJECT OF ELECTRICAL ENG (B.TECH)
Difference between shunt, PMG and AREP excitation. Which is the most reliable between PMG and AREP.
what is the difference between RMS & TRUE RMS VOLTAGE
Advantages/Disadvantages of earthing of neutral bus on MSB instead of separate neutral earthing for transformer/DG sets feeding to MSB
What is the meaning of floating point earthing in battery backed systems ?
When we need up only in o/p 440v, so why we use directly in 11kva in input?
how can we phase identification in a distribution line,how we recognise that which phase is coming for a house hold connection.help me............
what is the voltage rating of chiller unit sensors
How to apply 'c' license and also explain what is difference between 'c' and 'b'license.i am also working in one of the private company.i have finished my diploma in 2014 .i have already finished in ITI electrician course.....
how to calulate short circuit current for the following: 1.cable connecting 11KV of 22KV/11KV transformer to 11Kv of 11KV/415V transformer 2.what cable size should i use.
what is LSR?
what is meant by moulded case circuit breaker ?
What is slip in an induction motor?
what is the difference between droop mode and ischnorous mode in thermal powerplant?