Difference between the setting time and hardenin time of
concrete
Answer Posted / sujit ( hari machines)
setting time is taken by concrete to its minimum strength
in 7 days. harden time is time taken by concrete to its
maximum strength.
| Is This Answer Correct ? | 5 Yes | 10 No |
Post New Answer View All Answers
how much deduction will be in 32 mm dia HYSD steel bar for 45 and 90 degree bend
Why Vitrified tile are getting pop up.
What in your opinion makes you the most suitably qualified candidate for this post of civil engineering technician?
hii.plz send me hpcl placement papers for officers trainees for graduate engg plz my email id is ajm_knit@yahoo.com
what is conventional shuttering rate per square feet of built up area? what is Mivan shuttering rate per square feet of built up area? what is coupler shuttering rate per square feet of built up area?
how to determine H- zone in a column? where it will occur?
Why should pumping be not used in case of concreting work?
What is meant by cad?
What is the nature of duties & responsibilites senior civil engineer ?what is self confident & satisfaction should be a senior civil engineer?
What is the Hardness of M-40 grade concrete, general and theoratical
why development length = 50D . why not 100D
What is the zero value in quantity surveying
What are the joints wants to made in masonry where door opening, arches like etc..
Elaborate advantages & disadvantages of using crusher dust instead of sand in rcc work.
what is meaning of inverted beam.is it way to provide double mat in slab one at bottom and another at topif we go for provision of inverted beam. shall we construct structure with out plinth beam for us we have to construct small bus shelter