Laboratory experiments conducted in Mumbai on a particular
mix showed a
strength of 33 MP a for a fully matured concrete. Find
whether formworm
can be removed for an identical concrete placed at Jammu at
the age of 15
days when the average temperature is 60C. The stripping
stress in concrete

Answer Posted / buntychandwani

First thing the question is not completely and correctely
typed. The stripping stress in concrete in missing and also
how 60 deg temp will be possible in Jammu & Kashmir.
Let us connsider the Stripping stress of concrete as 25 Mpa
and average temp is 6 deg.

Now,

Maturity = Submission (time x temp)
= 15 x 24 x [6 - (11)]
= 6120 deg CH

Plowman's Constant given as A = 21 and B = 61


Se/S 15 = A + B Log10 [ M /1000]

Percentage of strength = 21 + 61 log(6120/1000)
= 68.99

The strength of Concrete at 15 days = 33 x (68.99/100)

= 22.76 Mpa

Since the strength of concrete is less than the stress to
which it is likely to be subjectd while stripping the
formwork, the concrete may fail. Therefore, the formwork
cannot be removed at 15 days time.

Is This Answer Correct ?    1 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is dead load impact load live load

1376


Why was the empire state building made of steel?

685


What is kn measurement?

744


how many spacers we need for 1 ton reinforcement? aprox.

4921


What are the steps involved in the concreting process?

875






how much repeitation for conventional and maivan formwork?

1594


What is type failure of road surface? how to repair the failure of road surface?

1984


what is E VALUE FOR WOOD

1533


How much does it cost for a R.C.C cover slab of size (450mmX 600mmx 100mm) double rf net given in feets using hand mix concrete?

1447


how can we calculate steel value, depending on load

1758


What is the outturn of Ceiling plastering

2860


Pile height is 4.3m. 2nos. under reammer. bulb nose is 75mm and height is 400mm. pile dia is 375mm and overall dia 940mm.pls. help to calculate concrete in pile and bulbs separately. What is formula for bulb volume calculation ?

1285


Explain what is the difference between built area and super built up area?

699


Explain what are the phases inspections are done by local authority while construction?

752


flow of fluid takes place viscosity compressibilityu surface tension deformation under shear force

1506