what is lead time, planning time, planning fence time ?
Answer Posted / girish pawar
Lead Time :: It is the total time required, by which
product is ready for use (manufacturing time +inspection +
handling.. etc)
Planning Time Fence: It is the time horizon which can
restrict the application area of the MRP. that is , there
will not be automatic changes to the Dates and quantities
within this Planning time fence ,during planning run.
It starts from current date to the number of days in future
specified as planning time fence as in work days .
Example >>> suppose , today is 13 January, and your
planning time fence is 5 days , then there will not be any
automatic changes during planning run between
13 Jan-to 18 January. And one day before the planning time
fence , that is on 17 january in our example ,the planned
orders are automatically get confirmed .
| Is This Answer Correct ? | 13 Yes | 0 No |
Post New Answer View All Answers
What are dynamic actions? Give a few examples. What are it’s you used in them?
Special Procurement type 40 – proc. form alt. plant
What is requirement class and requirement type?
What is the use of mrp pp evaluations?
If there are some errors in goods movements, and less stock of material consumed, how can we solve that problem in sap ?
In sap-pp what are the costing parameters?
What is recursive BOM
IM GOING TO GO FOR AN INTERVEIW SOON AND I WANT TO KNOW WHAT SAP PP INTERVEIW QUESTIONS ARE LIKE. I DONT HAVE A REALTIME EXPERIENCE THOUGH. ITS MY FIRST TIME
What is MTS and MTO and the difference between them?
Can we create production order without bom and routing ?
How to delete a group of products that was created in screen mc84 ?
What are the keyfields found in mrp view 1?
How do I find which is the recurrent item in a production order? In the missing material analisys I got message MF 331, but the BOM or the production order don'thave any recurrent item Thanks
How system calculate the actual cost?
What does the use of ms70 followed by mcec get you?