Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

What height of a 3.5 m high 300 x300 mm proposed col. can
be casted at a time ?

Answer Posted / sjtbehera

According to IS code In acolumn minimum height of casting
is 1200mm or 4' (apporox)

Is This Answer Correct ?    18 Yes 4 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Define current ucs?

1441


How to calculate(Thumb rule) the consumption of steel per cubic meter for different concrete members. 

3353


What are the different types of foundation?

1366


What is the difference between one-way slab and two-way slab?

1319


What is Architect-Prepared Contract?

1186


Why are steel plates inserted inside bearings in elastomeric bearings?

1174


yasser arfatcompleted his degree in civil from which university

2271


how to find out hard strata in bored pile when the DMC method adopted.

6076


how to calcualate the amount of stone,cement,sand required for 1cum of 450mm thick ruble stond masonary with ratio1:5, please me an answer with dtailed step

2175


What are segregation and bleeding?

1197


Will going from a 3-tap to 6-tap increase water pressure?

1068


what is work of planning deptt. in any construction compny (in road project)

2452


What is the purpose of Chipping in the heavy foundation?

1619


I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

2089


How to determine thee cut length for steel reinforcement bars in R.C.C design

1562