How do speedup the project delivery without affecting the
cost?

Answer Posted / sanjay ursal

The procedure is called Fast Tracking. Starting Sucessor
activities before the completion of their Predessor
activity.

Fast tracking is risky, needs very good coordination and
may involve rework.

This can be achieved only incase you are a different set of
resources on the predecessor and sucessor activities also
incase of any free resources u can utilize to do this.

Is This Answer Correct ?    14 Yes 6 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Write the test cases for instr function?

650


What is the role of CLR in ASP.NET?

3201


Tell about current project ?

2224


Explain dll hell?

667


I want question and paper based MS Projects. Also is there any exam which microsoft conduct for Ms Project professional to issue certification?

2175






Test the save dialog in Notepad?

4191


How do you create the Software Project Management Plan (SPMP)?

4045


What training have you undergone in project planning?

3332


create a flow diagram up to 2 levels for hospital management

3232


Write the instr function.

745


Given a MAKEFILE (yeah a makefile), design the data structure that a parser would create and then write code that iterates over that data structure executing commands if needed.

5172


Assignment A software house got a project to automate sales/purchase department of a furniture store. The store management is clearly transferred their requirements to the software house management. There is no chance of changing the requirements afterwards. Software house management use waterfall process model to make the project. Given is the progress flow of water-fall process model In waterfall process model, the deliverable (document) produced in one phase serves as an input to the next phase. Suppose you are a project manager who is leading this project. It is decided to work and complete the project using waterfall process model approach. You are required to develop a plan in which the key task is to decide the deliverable that should be built during and after completion of each phase. Also give a description or required contents that must be included in those deliverables. You are not supposed to make the complete project. All you are required to do is to make a Project plan. In that, you need to give a set of deliverables (documents) which according to you, should be developed in each of the phase (Requirements, Designing, implementation, Testing, Maintenance). Also provide contents which should be there in each deliverable. The contents should be clear and have brief explanation. Note:: There are one folder and one file in the attached folder. The file is named as Assignment 4 write-up which is your assignment write-up. The other folder named Project deliverables is the folder in which you are required to organize and place your deliverables. Name of the document/deliverable saved in each folder should be mentioned in the file named checklist (This file is placed in the “Project deliverables” folder) For Example If you produce a deliverable named Requirement Specification (RS) in the “Requirements” phase. You need to do following tasks 1) Finalize the RS contents 2) Save the file in sub-folder named Requirements 3) Write the name of this document in the checklist file under the heading Requirements. Similarly, you need to make and save deliverables of each phase. Not all phases contain one deliverable. There must be some phases having more than one deliverables. PLEASE SIR PRIVIDE ME THE CHECK LIST FOR GIVE SENERION ? CHECKLIST ARE: 1-Requirements 2- Designing 3- Implementation 4- Testing 5- Maintenance

6493


When you come in to the office, how do you know what you have to do during the day?

1934


How do you rate yourself in c#,vb.net,Asp.net,oracle,sql server ?

4980


How are the team members kept informed about the current status of the project?

2180