Answer Posted / manikandan.d
PLC can control only one system at a time where as DCS can
control multisystem at a time DCS has its own database while
PLC does not. it has to use SCADA or MMI. scan time for PLC
is less than 10ms where as scan time for DCS is less than 100ms.
Is This Answer Correct ? | 29 Yes | 12 No |
Post New Answer View All Answers
Regarding , there is an air cooler which control the fans(50% of AV FANS) by temperature in outlet , and the louver of Air cooler is controlled by HIC from control system , So if on Air cooler we will consider 2 individual I/P converter or positioner?
Calibration of controller (pneumatic)
How to calculate mmwc values into tonnes?
what is the process to make control schematic ?
Can anybody please let me know Orifice plate sizing calculation formula and step by step procedure
Q- Control problem are mainly classified in _____ types. a-)4 b-)3 c-)6 d-)nono of these Few of them i know is 1- regulator type problem (eg- Air conditioner) 2- tracking problem (eg missile trcking problem) 3- sybernatics 4- optimal control problem
how to measure draft pressure in transmitter pl. give its single line digram
Explain the combusion chamber
what can of fault ofently come in vibration mesurement?
Can u tell me the principle of the tc,rtd,level switch,pressure switch ,transmitter(pr flow level temp.),vibration...plz
where uses EXe /EXd/Exo/Exn/Exp/Exq/EXia
In power plant to measure vibration of a turbine we install sensors. Before install this sensor we have to set gap voltage. What is meant by gap voltage and its use?
Tr. Wiring for calibration.
What is the meaning of wet leg
What are the application of bernoulli’s theorem?