How can we calculate one operator can 2 to 3 machine?
Is it any calculation for this.
Answer Posted / engr. ansari
The calculation is dependent on the operations cycle times,
if you are doing line balancing on the basis of
machine/operations cycle time check the under utilize OR
excessive utilize work content and distribute it
accordingly, if 2~3 operations have very less time in
sequance with the next operation, one operator can perform
on 2 or 3 machines to make the more efficent line.
| Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
reversing of each word in the string
What is industrial engineering? How important are statistics in industrial engineering?
whats te normal transformer current rating
how do you adjust pump impeller clearance?
what is alternater & engine genral protection?
How capacitor bank can prove superior to synchronous condensers with respect to power factor correction?
What is alpha test in alumina powder?
How capacitor bank can prove superior to synchronous condensers w.r.t. power factor correction??
What is the specification of transformer?
QTP related question= What is input action parameters and what is output action parameters ?
what is fixed bearing?
start-up procedure of a centrifugal compressor
what is a benifit to configure site to site vpn ?
what is machine tpm
where is fixed bearing located?