RCC colums of 15"X9" each, roof height 10.5'ft, total
pillars 12 nons. Span between pillar to pillar is 14/20/20
length wise and 17/14 width wise. Total Slab area 2400 sft
and plinth area is 1900 sft. beams are 12"X12". kindly
calculate load factor per sqft.
Answer Posted / sujit
calculating load factor
incase of astructure some live load and dead load is
calculating
As per IS code - take live load-4.0 kn/Sqm
terrace finish- 1.5 kn/sqm
floor finish - 1.0kn/sqm
water proofing- 2.0 kn/sqm
----------------------------
total load-8.5 kn/sqm
i conver all ft ad inch to mt and mm
dead load of column or its own weight-
.38x.228x25x12=25.992kn/m 25kn/m recc wight
beam weight- .304x.304x25x15.732x3=109.041
- .304x.304x25x29.5x4=272.62
slab weght- 222.22x.100x25= 555
------------------------------------------------------
total weight= 962.653kn/sqm
total dead load+ live load=962.653+8.5 = 971.153kn/sqm
so per sqm load factor = 971.153 kn /sqm
you can easily convert it per sqft
| Is This Answer Correct ? | 32 Yes | 4 No |
Post New Answer View All Answers
How many days should curing of plastering, brick work and concrete
Water filter calculation formula
You have 3 snd sample of different FM=0.21,FM=0.95,FM=2.90 which one is suitable for a)plastering on R.C.C b)plastering on masonary wall c)concreting column d)concreting of bored pile.also justify your answer.
what is the use of steel rods of 16mm or 20mm used for 4.45mts for closing gutter.one mate consumes how many kgs with a gap of 6inches.
Hi how r u ? hope you are fine there . Please can u tell me tha Design life of Buildings as Per ACI CODE 318-99. It will be a pleasure for me .Thanks in advance
How to Know that veriation acceptable in CPWD Work Of 1:6 Cement Mortor Received Lab test report.
what is the difference between tsp & tower
what is zone a n zone b?why the spacing of ring in zone a less.n zone b high?
Which are the top apps for you civil engineering?
What things you need to take care of before building a kitchen island?
How to arrive d*d/162 , for finding the kg per meter , wt of steel
How to calculate brick work quantity?? Block work quantity??
Special thing in designing a overhead reservoir ? which is different from an ordinary design
How to do rate analysis for concrete work including shuttering work?
What is the strongest bridge for a school contest?