my scenario is repetitive manufacturing (REM) make-to-stock
(MTS)production for sugar industry. What are the things, I
have to customize for this scenario, to the PP point of
view..
Answer Posted / kavan patel
Step 1: Create REM Profile using SPRO (TC: OSPT)
SPROàProductionàRep ManufacturingàControl Dataà Create REM
Profile Using Wizard.
Save the profile and exit from SPRO.
1. Create Material Master with Fert and ROH as usual.
2. Create BOM as Usual.
3. Create Production Line with Capacity Category as :
0007 (i.e normal work center)
4. Create Rate Routing for Fert Material using TC:
CA21
5. Go to Change Material Master (Fert Material ) and
Attach REM Profile, Mark tick indicator for REM
Manufacturing. In MRP-4 View.
6. Create Production Version for this Fert material.
Select BOM, Select Rate Routing with No.
Step No: 2
Create Independent Requirements TC: MD61
Step No:3
Run MRP TC: MD02
Step No: 4
Go to Planning Table TC: MF50 and assign the quantities to
production line.
Step No: 5
Run Schedule Quantities are assigned and go to MD04 all
planned order are converted to RS Qty.
Step No 6:
Create Product Cost Collector for Fert Material: TC: KKF6N
Step 7:
Do the Back flush Using TC: MFBF
Enter and save the file….
Is This Answer Correct ? | 18 Yes | 1 No |
Post New Answer View All Answers
We defined sop in months. However, during sop transfer to demand management, our independent requirements are appearing in weeks. How can we correct this from weeks into months?
What are all the ‘technical types of bom’?
How to create PRT master record?
What general data appears on basic data screen?
Special Procurement type 40 – proc. form alt. plant
Both labor and machine categories exist. How would you calculate the process time?
What is a 'product hierarchy'?
what is the major ticket in your experience
Difference between MD01, MD02 and MD03.
What are dynamic actions? Give a few examples. What are it’s you used in them?
What is serial number and where you will be configure
Scheduling times can be defined in the material master record by?
What is Schedule Margin key. How floats works in scheduling?
What are all the 'sub-components' of production orders?
list the important tables used in pp.