First symbol/symbols, capital letters: HV winding connection.
Second symbol/symbols, small letters: LV winding connection.
Third symbol, number: Phase displacement expressed as the
clock hour number.
Winding connection designations
High Voltage Always capital letters
Delta - D
Star - S
Interconnected star - Z
Neutral brought out - N
Low voltage Always small letters
Delta - d
Star - s
Interconnected star - z
Neutral brought out - n
Phase displacement
Phase rotation is always anti-clockwise. (international
adopted convention)
Use the hour indicator as the indicating phase displacement
angle. Because there are 12 hours on a clock, and a circle
consists out of 360°, each hour represents 30°.
Thus 1 = 30°, 2 = 60°, 3 = 90°, 6 = 180° and 12 = 0° or 360°.
The minute hand is set on 12 o'clock and replaces the line
to neutral voltage (sometimes imaginary) of the HV winding.
This position is always the reference point.
Because rotation is anti-clockwise, 1 = 30° lagging (LV lags
HV with 30°)and 11 = 330° lagging or 30° leading (LV leads
HV with 30°)
To summarise:
Dyn11
Delta connected HV winding, star connected LV winding with
neutral brought out, LV is leading HV with 30°
| Is This Answer Correct ? | 302 Yes | 15 No |
Post New Answer View All Answers
how does ELR works? explain
What is the difference between circuit breaker and isolator
how to design the heater in temperature control unit to heat 50KL of water?
What do you mean by passive circuit elements and why these are called passive?
why we use condenser in the thermal power plant, althrough the same vapour will be again heated
is this the formula of building wiring to get the main breaker.Watts/volts*.8%+higher motor*(25%)=ampere. yes or no or send the correct formula for building wiring.
why the arc welding machines require parallel earthing systems? ie why each machines are connected to earth pit by separate wires during earthing? wats it adavantages?
Sir, I have applied for the of Jr.engineer(Electrical & Electronics) & ASST. LOCO PILOT at ALL RRB BOARDS. please send me all RRB Boards solved papers in the year of 2001 tO till date. i requested send me the papers to my id as soon as possible (jet_0991@yahoo.com). (This is very urgent) Thank You,
2. What are the parameters of EHT sub-station?
how invertor convert the dc into ac give brif detail
what is advertised hop count
How seriving & testing of the HT & LT breakers are done. What are the standard Ir values on which we can come to know the test is passed or failed?
I'm looking for a softcopy manual set for a Credence ASL- 3000. Anyone know where I can get it?
how many parameters can integrate with fire alarm basically ?
why should the primary of transformer be connected in delta in a heat run test?