for calculation lets take 1: ratio plastering 12mm th.
for 1 sqm
so total volume = .012x1=.012 cum
increase by 20% fir filling
depression= .012+.012x1/5=.0144cum in wet condition
when dry increase the volume by 1/3rd.
.0144+1/3x.0144=.0576 cum
summation of proportion=7
cement=.0576/7=.0082cum=.237 kg
sand=..0082x6=.492 cum
| Is This Answer Correct ? | 26 Yes | 16 No |
Post New Answer View All Answers
Why reinforcement done in shorter span in two way slabs
1m square 20mm plastering how much of water need curing work
which red: used in roof teping, then use only cement
please send me bhel questions on rupesh.017@rediffmail.com
how much cement sand n bricks required in im3?and how much in plaster?
What is Joule Brayton Cycle?
What is Critical path in Ms-Project ?
What the advantages and disadvantage of using 90mm and 100mm bricks for a wall of a house? Thanks for any input.
Why are separation membranes used between concrete pavement slab and sub-base?
door and window wood work calculations and different methods
Explain the latest method to detect a crack in a building?
What is unit weight of normal concrete?
A rock anchor 3 1/2” in diameter is placed in rock. The which has an allowable shear strength of 1200 psi. Determine the required anchorage length to safely carry a 80 ton load using a 2.0:1 F.S
What is bylayer?
How to calculate the crank rod in slab