Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

why we are doing post tensioning in beams and slabs.
it is economical compare to rcc? how?

Answer Posted / vikram jain

Dear Friend,

It is very economical as compared to RCC.

1.) Early Post-Tensioning allows the formwork to be stripped and re-deployed quickly. Significant saving on material, up to 30% on concrete alone with longer spans, fewer columns & thinner slabs producing lighter overall structure and reducing foundation cost.

2.) Joint free ground slabs up to 10000 m&#65394; and true & level floor – ideal for automated ware housing and super markets.

3.) A facility to span over poor ground conditions with full resistance to mining subsidence.

3.) Water proof floors to eliminate unsightly staining of concrete fascias. Thinner slabs give more head room.

4.) Flexibility- Internal layout flexibility is greatly increased, making it much easier to place or reposition partitions with formwork stripping and redeploying quickly and with less steel & concrete construction work is faster than R.C.C. construction.

5.) Spans up to 50% longer than those using RCC can be constructed with fewer support columns.

6.) Offers resistance to cracking and water seepage due to limited deflection and highly compressive characteristics of prestressed concrete structure.

7.) In Post Tensioned slabs, slab is always tested for stresses that are supposed to be come on slab.

8.) Thinner Slabs – post tensioned slabs of thin concrete plates may be used to reduce storey height in multistory buildings.

Is This Answer Correct ?    6 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How much cement and water required for cement selery????

1945


I used Etabs software to analyse a high-rise building. And I want to use templated UBC-codes inside to calculate the Seismic load. My question is: whether or not I have to control the seismic load by base shear load which is manual calculation? (just for more clarification: I can control this by input the scale factor into Eartquake definition in Etabs) I would highly appreciate your answer.

6074


Required concret Surface Temperature prior to coating of epoxy pain with references ASTM or ACI whatever

2244


As we know that steel is a tension member but why we are using STRUCTURE STEEL as a COLUMN (Without concrete) where column is a compression member and compression strength of steel is very low

1617


How to calculate the force on a column of three story building. What should be the base concrete height?.

2215


How to find coloumn vertical cut length floor to floor & lap + bend or anything plz clearfiy

2035


where tie beam is used? what is the pupose? what dimension of tie beam can provided and number and diameter of steel bars to be used between the columns of 1333mm and 1400.

3430


Define unit atmospheric pressure? Difference between gauge pressure, absolute pressure?

2157


1. For 10sq.m area(47 kg bitumen contain) of 45 mm thick bitumen mix layer..how much bitumen is required for 1600 sq.m and how much aggregate need for that ?? 2. And much tonnage of bitumen mix required for 10 sq.m area of 45 mm thick. Please give answer...

2045


specifications of fe500 steel

3527


how to calculate spacing rod in column

1952


How much cement and sand are required for 1 square feet of plaster at a thickness of 15 mm at a ratio of 1:4?

1670


How will you reduce the concrete flow after mixing the concrete

2195


for 16mm thick cement plastring 1:6 on 100 Sq.m.New brick work,the quantity of cement required is.

2009


how to control PQI (Project Quality Index)

10860