when testing will starts in a project?
Answer Posted / pramila
<< Re: when testing will starts in a project?
Answer # 5
Hi,
Once the Requirements are based lined then only we can
go for testing
Regards,
Satya.K >>
This is wrong. once the requirments are based line u dont
start testing. u need to get the coding done n the build
for the test. if the test team is involved in requirment
gathering fine they start to do test on the requirments but
not after based line the document.
please any one correct me if am wrong
| Is This Answer Correct ? | 0 Yes | 2 No |
Post New Answer View All Answers
Write 10 test scenarios to test remember me checkbox present in login window
Hi Could someone please provide Siebel Testing Interview questions for 5 years exp.
Which was the most interesting bug you found.
what are the various techniques you will use as soon as the srs was given to you to speedup the testing?
Hi , Please send me the interview questions which were asked in manual testing mainly the test cases asked to write in interview.
Can you please explain about the erp project
what is the difference between website and web based application ?
wat is test management ?what are the components available in test management?
1.Acceptance testing involves procedures for identifying acceptance criteria for interim life cycle products and for accepting them.is that? 2.Acceptance testing occurs only at the end point of the development process; it should be an ongoing activity that test both interim and final products.is it?
Explain Single View Testing ?
what is the difference between test case and result matrix
What do you like about computers?
Why would we not include these?
test cases for compose functionality of gmail
Explain accessibility testing and its importance in the present scenario.