Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

We have 2 no. 4MW DG set. and GEB supply.
But, we running, only 1 DG set. when we done APFC/Power
factor setting : 0.90, then winding temp. Low. but when
setting done : 0.83, then Winding temp. increase.
WHY Why ? ? ?, plz give me answer.

Answer Posted / suthan prabhu

The reacive power taken by the load will be same but the
current supplied by the source will increase bcoz the p.f
is decreased from 0.9 to 0.83.hence the winding temperature
increased.

Is This Answer Correct ?    5 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is Traction? 1KVA Alternator, How much urrent taken?

2195


How many kinds of E.L.C.B and how to work E.L.C.B

2094


sir, iam a electrical engg graduate and i want to go in automation sector and for this i have decided to do industrial training for this,plz suggest me some good institute for the same in delhi,ncr. my degree percentage is 58%, can i get job after doing training, plz help....

2090


STATE USE OF ARC RUNNERS & SPLITTERS ?

1997


what are the installation procedure of high voltage power transformer,CT,CB&PT?

2123


On what basis do you decide the ONAN (Oil Natural air natural) or Dry type transformer for a project?

1654


Please send 110 kv sb station full single line drawing(sld)

2521


i want design of D.C.MOTOR 1HP 960RPM AND 2HP 960RPM ITS URRGENT

2017


What is the classification of hydro projects based on installed capacity?

1241


WHAT SHOULD BE THE BEST CURRENT RATINGS (PRIMARY / SECONDARY)FOR A CT INSTALLED AT THE INCOMING 11KV PANE? WILL IT BE CALCULATED ON THE BASES OF MAXIMUM DEMANT VALUE OR ON SUM OF ALL TRANSFORMER'S KVA? NOMALLY MAX DEMAND REPRESENT THE MAXIMUM OPERATING LOAD OF THE PLANT AND TOTAL KVA OF (SAY 5 NUMBERS TRANSFORMERS) REPRESENT THE CONNECTED LOAD. WHICH i.e. MAX DEMAND KVA OR CONNECTED KVA ARE BETTER TO USE FOR CT CURRENT CALCULATION? PLEASE ANSWER.

1963


if you are in a software company,then why do you want to come in a core company like sail, ntpc(where lots of trouble like tension but you have a good life in a it company) ?

1962


what should be the no load current for 3 phase ac motors ranging from 5 kw to 1000kw?

1844


when will be the iocl interview results i faced interview on 8th september 2008 iam from electrical branch i faced interview for the post of electrical engineer??????????????????????//

2089


What are operating procudures & Safety precautions to be observed while operating OLTC in manual mode ?

2053


State the points to be considered for selecting a particular type wiring.

2128