Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

Hod do u calculate cable size for underground laying and
the factors effecting/influencing it??

Answer Posted / madhav

While other answers are general procedures for selection of
cable, underground cable laying is different, AFTER having
taken the above factors into consideration.

The laying of underground cable should also consider the
permissible conductor temperatures, ambient temperature,
number of cores and mode of laying (single cores or
multicores), etc. The maximum current carrying capacity
also varies with the type of cables and its insulation
properties.

Cable laying is also of several types. In case of single
core cables, they could either be close together or
seperated by one diameter of the cable. That could also
cause differences in current carrying capacities.

In general, for a loaded 5 core cable when laid in ground,
the derating factor could be 0.7 times the rated current
carrying capacity of the cable.

Is This Answer Correct ?    5 Yes 5 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Please help me regarding my one concern. - During earth pit testing we noticed that the Clean earth pit and dirty earth pit showing continuity (Resistance value - 5ohm) . I want to know that if both earth pit have separate location and there is not internal looping between PIT then why such continuity is showing on it . Because of this issue the field side all earthing point showing short. In PLC panel we are providing two types of earthing cable which is coming from separate earth pit (Clean and Dirty earth pit) because of earth PIT showing short our PLC is not complying spec . please help regarding this issues.

1590


Hello Friends, How can we recognize the CT Star Point is S1 or S2 in case of Electro Mechanical Relays and what is meant by Restraining coil in relays and what is the purpose of that.. thank you in advance..

2167


how we start 40w tube light with 4 diodes,2capacitors,1 choke and without starter.(a product avilable in market which lights burnt tube lights also)

2039


by using pump duty, how we will can calculate the motor duty(KW)? is there any standard or formula.

1975


How to select HT/MV cable size ?

2470


suri transmission

4751


at what basis/standard we have to arrive the current density of aluminium/ copper in busbar?

2123


what is differentila pilot supervision in the incomer control panel in the power station?

2099


how to increase or decrease speed in DC shunt motor by DC convertor

2277


why lightning arrestor are made in two stack of insulator but why not cvt

2078


I have done my m.tech in electrical engg discipline. Can any one please suggest me how should I prepare for getting into phd in iit or nit.How should I prepare for getting into lecturership

1698


What should be the Sandwitch type Al. bus bar capacity for 2 M.W.Gen. set, having continuous full load current- 3463 Amps,ambient temp.- 50 Deg. C., Required temp. raise-20 deg.C., it will run 24 hrs, 365 days on full load, required highly reliable.

2683


What is the difference between line drop and percentage line drop?

1566


describe the constructional features of an auto transformer and its principle operation

2358


Following test should be conducted to find out relative polarity of transformenr terminals A no load test B back to back test C phasing out test D none of above

2216