WHY DO WE PROVIDE DEVELOPEMENT LENGTH AND EXTRA BARS AT TOP
Answer Posted / muqdad jawad jafar
negative moment normally require providing extra additional
bar at the top of horizontal concrete casted members that
often positioned within the area supported by column/wall.
the top extra length should exceed the inflection point
between negative and posetive moment.
| Is This Answer Correct ? | 36 Yes | 3 No |
Post New Answer View All Answers
what are the strength theories for yeilding and fracture materials. state the theory more suited for 1. mild steel or 2. concrete
How musch steel i.e. angles, channels,and square pipes are required per square feet for a steel roof of residential two storied building?
what is work of planning deptt. in any construction compny (in road project)
A 16 pile group, consisting of diameter concrete piles, were cast in situ in a clayey soil whose unconfined compressive strength is 1100 psf. Each pile is 60 ft long and the pile spacing is 2.5 times the pile diameter.The water table is at the ground surface and saturated unit weight of the clay is 118 lb/cu.ft. using a factor of safety 3 and a reduction factor =0.45, compute the allowable capacity of the piles acting as individuals
Q 1) 1 Mason and 2 LABOUR / _________CUM brick work Q 2) 1 Mason and 1 LABOUR / _________SQ FT Plaster work Q 3) 1 Carpenter & 2 Labour/_________SQ FT shuttering work Q 4) 100 SQ FT roof slab concreting ____________mason and labour required
what is the coefficient for running feet to cft coversion both area and price
Required amount of Steel bars, cement/ square feet for roofing of residential building upto 3rd floor.
What is the ideal size of the living room ranges from small to large size?
Design a shear wall of length 4.20 m and thickness of 250mm subjected to the following forces.Assume Fck = 25Mpa and Fy = 415Mpa and the wall is a high wall with central part 3440mm x 250mm and two 380mm x 760mm strong bands at each end with following loading. S.No. Loading Axial force Moment Shear 1 DL+LL 1950 600 20 2 Seismic load 250 4800 700
"how can we find the approximate quantity of materials using in a building or total Expenditure in percentage for rough estimate after known the construction area(sqm)".please if you know something about that please post the answer.
how to calculate the material from ratio of work PCC, RRM,POINTING, RCC
What is the snap size in civil and how can we create it?
how many men days of loburs and masons are requirete for 1 cum,pcc (1:2:4),Pcc(1:3:6) and Pcc(1:4:8) thanking you
What is the difference between yeild strength and compressive strength of steel???
Where will be the maximum bending moment in a TEE Beam?