Answer Posted / mathan
loop checking means ,after installation of instruments we
must check full loop(instrument-junction box-control room)
to ensure that whether the instruments are working properly
or not, and whether is it passing the signal or not,whether
is it receiving the signal or not. before we start the
plant we need to check loop..
during the loop check we give some known input
and check the corresponding output at other side(control
room)..if the output is corresponding to input, the loop is
ok..if not means, something fault inbetween the loop.
for example.if you want to check ON/OFF control
valve,during the loop check,when you give 24v dc from
control room ,the valve must open fully, and when you give
0v dc the valve must close.
| Is This Answer Correct ? | 274 Yes | 10 No |
Post New Answer View All Answers
all questions related to instrument technician in any offshore oil and gas company.
1.can you use SCADA instead of DCS,DCS instead SCADA 2.Difference between DCS and PLC,can their role be reversed i.e. role interchange 3.Difference between RTU and PLC
What is compensation for flow ? Why we use compensation ? What are the factors of different compensation ? We not use then what problems may happen ?
For what reason would you possibly be compelled to make use of a Smith Predictor. Explain the idea behind the operation of this device.
can any send me a forbes marshall dtron 316 manual
How does your previous experience relate to the job you are applying for ?
How servomotor controls throttle valve of TURBINE?
how do i tune dearator pr control valve using PID. we set the set point is 0.6kg/cm2 now i want 0.5 to 0.7kg/cm2 limits so what should i give p,i,d values. then pls explain how do set pid values for control valve tuning?
What are the charcterstics of a P&ID controller block for Governor speed raise or lower for a load sharing functionality between 4 Gas turbines in droop mode.
OBJECTIVE TYPE QUESTIONS OF ANALYTICAL INSTRUMENTATION
I am having a Phoenix digital to modbus converter. The o/p of the same is connected to flow computer FB407. But the digital signals are updated only after one minute in the flow computer. what may be the cause of delay in communication? Flow computer is having a scanning period of less than 1 sec.
For crude application in floating roof tank, how to calibrate a DP Transmitter? How is the floating roof weight considered?
How to control flow variations in magnetic flow maters..... When i will provide proper earthing?
Can any body tell me about SAP MAINTINANCE MODULE. WHAT IS its function and application. And study material Source about it. I shall be very thankful.
why orfice is not used for main steam flow calculation