what is a project management?

Answer Posted / pramod pudur

Project Management is the application of knowledge, skills,
tools and techniques to project the activities to meet the
project requirements.
Project management is accomplished through the appropriate
application and integration of 42 logically grouped project
management processes comprising of 5 process groups
(Initiation, Planning, Execution, Monitoring and Control
and Closing)

Is This Answer Correct ?    43 Yes 7 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

You are working on a project that was proceeding well until a manufacturing glitch occurred that requires corrective action. It turns out the glitch was an unintentional enhancement to the product, and the marketing people are absolutely crazy about its potential. The corrective action is canceled, and you continue to produce the product with the newly discovered enhancement. As the project manager, you know that a change has occurred to the product scope as the glitch changed the characteristics of the product. Which of the following is true? A. Changes to product scope are reflected in the project scope. B. Changes to product scope are reflected in the integrated change control plan. C. Changes to product scope are a result of changes to the product description. D. Changes to product scope are a result of corrective action.

554


What are the qualities of a good project manager?

505


You’re promised your team two days of paid time off plus a week’s training in the latest technology of their choice if they complete their project ahead of schedule. This is an example of which of the following? A. Achievement theory B. Expectancy theory C. Maslow's theory D. Contingency theory

757


All of the following are true regarding the tools and techniques of Activity Sequencing except: A. GERT uses analogous methods. B. GERT allows for loops. C. GERT is a conditional diagramming method. D. GERT allows for conditional branches.

621


You are the project manager for Design Your Web Site, Inc. Your company is designing the website for a national grocery store chain. You have your activity list in hand and several time estimates and are ready to diagram the activity dependencies. You should use which of the following? A. PDM techniques B. PDM or ADM techniques C. AON techniques D. ADM techniques

513






The lowest level of the WBS is called what? A. Code of accounts B. Requirement C. Milestone D. Work package

611


You are a project manager working in the automotive industry. You are performing quality control and decide to rank order the frequency of problem occurrences over time using which of the following: A. Control chart B. Pareto diagram C. Cause-and-effect diagram D. Scatter diagram

894


You are the project manager for Changing Tides video games. You have produced a project network diagram and have updated the activity list. Which process have you just finished? A. The Activity Sequencing process, which identifies all the specific activities of the project B. The Activity Sequencing process, which identifies all the activity dependencies C. The Activity Duration Estimating process, which diagrams project network time estimates D. The Activity Duration Estimating process, which identifies all the dependent activities of the project

517


The tools and techniques of the Source Selection process include all of the following except: A. Contract negotiation B. Correspondence C. Independent estimates D. Screening system

500


You have been hired as a contract project manager for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for their customers. Customers must pre-register before being allowed to order wine over the Internet so that legal age can be established. You tested using data from Grapevine's existing database. This new module cannot be tested until the data from the existing system is loaded. This is an example of which of the following? A. Preferential logic B. Soft logic C. Discretionary dependency D. Hard logic

695


Describe the risk in software engineering.

491


Your project is in the Scope Definition process. You've just completed the WBS. Which of the following is true? A. The WBS breaks the project deliverables down to a level where alternatives identification can be used to determine how level two assignments should be made. B. The WBS breaks the project deliverables down to a level where project constraints and assumptions can be easily identified. C. The WBS breaks the project deliverables down to the work package level where product analysis can be documented. D. The WBS breaks the project deliverables down to the work package level where cost and time estimates can be easily determined and quality control measurements can be determined.

590


You are the project manager for a cable service provider. Your team members are amiable with each other and are careful to make project decisions jointly. Which of the following is true? A. They are in the smoothing stage of Team Development. B. They are in the norming stage of Team Development. C. They are in the forming stage of Team Development. D. They are in the forcing stage of Team Development.

537


What is the difference between risk impact and risk probability?

484


Explain the Principals of Management

598