what is a project management?

Answer Posted / ganga reddy

Project management is planning & monitoring the task as
per the requriemts and make them complete on time and with
in budget to get desired results.it plays a major role in
organisation build.

Is This Answer Correct ?    28 Yes 7 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What are the different software reengineering activities?

519


You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competing with another retail store for the option of opening two new stores in a foreign country. You've been told that it is culturally unacceptable to eat certain foods in this country. You know that one of these foods happens to be a secret ingredient in the pizza sauce. What is the most appropriate response? A. Inform the potential partners that your sauce recipe is secret, but you’re certain there are no forbidden ingredients in it. B. Inform the potential partners that you suspect there might be a forbidden ingredient in the sauce and you'll request an investigation to determine if any of them exist in the sauce. C. Inform the potential partners that a forbidden ingredient exists in the sauce and determine to work with them to come up with another ingredient to replace that one. D. Don't tell the potential partners about the ingredient because the sauce they'll be using in the stores is shipped to them already prepared in cans. They won't know the ingredient is in the sauce.

696


What are the tools and techniques of the Contract Administration process? A. Contract change control system, payment system, payment requests B. Contract change control system, contract negotiations, payment system C. Contract change control system, contract negotiations, contract changes D. Contract change control system, performance reporting, payment system

511


You need to convey some very complex, detailed information to the project stakeholders. The best method of communicating this kind of information is? A. Verbal B. Vertical C. Horizontal D. Written

539


Critical path tasks are those tasks that: A. Have equal pessimistic, optimistic, and most likely estimated times B. Have a float rime of zero C. Have the same start date D. Have multiple early start dates and early finish dates

565






How will prioritize tasks in your projects?

479


Which performance measurement tells us how much more of the budget is required to finish the project? A. ETC B. EV C. AC D. EAC

913


Project managers use this conflict resolution technique most often: A. Smoothing B. Confronting C. Naming D. Forcing

540


You do not expect the types of variances that have occurred on the project to date to continue. If BAC = 300, ETC = 275, PV= 300, AC = 200, EV = 250, and CPI = 1.25, what is the EAC? A. 240 B. 250 C. 475 D. 150

566


You are the project manager for Lucky Stars nightclubs. They specialize in live country and western band performances. Your newest project is in the Planning process. You are working on the WBS. The finance manager has given you a numbering system to assign to the WBS. Which of the following is true? A. The numbering system is a unique identifier known as the code of accounts, which is used to track the costs of the WBS elements. B. The numbering system is a unique identifier known as the WBS dictionary, which is used to track the descriptions of individual work elements. C. The numbering system is a unique identifier known as the code of accounts, which is used to track time and resource assignments for individual work elements. D. The numbering system is a unique identifier known as the WBS dictionary, which is used to assign quality control codes to the individual work elements. ?

522


Which of the following tools and techniques shows the impacts of one decision over another as well as the probability and cost of each risk along a logical path? A. Simulation B. Decision tree C. Probability/impact risk matrix D. Sensitivity analysis

538


How do you set goals for your team? And how do you track these goals?

535


All of the following are true regarding Pareto diagrams and Pareto theory except: A. Pareto diagrams are histograms. B. Pareto diagrams rank order factors. C. A small number of causes create the majority of problems. D. Pareto diagrams use two variables.

653


Your project was just completed. Due to some unfortunate circumstances, the project was delayed causing cost overruns at the end of the project. This information might be useful on future projects in all of the following activities except: A. Cost estimating B. Allocating resources C. Product verification D. Activity estimating

531


Which of the following is true regarding NPV? A. NPV assumes reinvestment at the cost of capital. B. NPV decisions should be made based on the highest value for all of the selections. C. NPV assumes reinvestment at the prevailing rate. D.NPV assumes reinvestment at the NPV rate.

557