my scenario is repetitive manufacturing (REM) make-to-stock
(MTS)production for sugar industry. What are the things, I
have to customize for this scenario, to the PP point of
view..
Answer Posted / sundhu
Hi,
To customize this first need to maintain the Master data,
1) Material Master-> MRP4-> create & add Producion version,
2) Define the BOM-> CS01.
3) Create a Rate Routing->CA21.
And in Transaction data,
1) Create a Planned independent Requirements->MD61,
2) Run MRP->MD02,
3) Review the capacity through Planning Table->MF50,
4) Finally can create the Product Cost Collector->KKF6N.
Note:
KKF6N is a integration between PP & FICO.
| Is This Answer Correct ? | 7 Yes | 2 No |
Post New Answer View All Answers
What parameters you maintain in “plant parameters” in configuration?
what do you mean by planning time horizon
What is mrp controller means?
What is the difference between stock transport order and stock transfer order?
Explain what is plm (product lifecycle management) in sap pp and what is the use?
Can we use the same routine for materials undergoing the same process/operations? Can we avoid separate routing for each and every material produced?
What is the use of mrp list?
Difference between Routing, Ref op set, Rate routing and Ref rate routing.
Difference between different strategy groups.
What is known as 'demand management'?
When you run MRP, What steps it Perform in Back ground or How do you schedule BG job for MRP
what does SAP business workflow do?
what do you mean by planning time fence
What is planned consumption and unplanned consumption?
What is mrp group and what is the use of it?