my scenario is repetitive manufacturing (REM) make-to-stock
(MTS)production for sugar industry. What are the things, I
have to customize for this scenario, to the PP point of
view..
Answer Posted / sundhu
Hi,
To customize this first need to maintain the Master data,
1) Material Master-> MRP4-> create & add Producion version,
2) Define the BOM-> CS01.
3) Create a Rate Routing->CA21.
And in Transaction data,
1) Create a Planned independent Requirements->MD61,
2) Run MRP->MD02,
3) Review the capacity through Planning Table->MF50,
4) Finally can create the Product Cost Collector->KKF6N.
Note:
KKF6N is a integration between PP & FICO.
| Is This Answer Correct ? | 7 Yes | 2 No |
Post New Answer View All Answers
What is standard order type
Are there any reports in sap to list of material requirement from ltp ?
Integration between PP and MM Module.
I have having 14 years manufacturing experence & 6 years in SAP-PP/QM.Was a core member during implementation.Now I want to work as Functional Consultant in SAP-PP/QM.What should I do for getting the jobs.
What is phantom item & sub contracting
Explain In-process inspection.
Explain what is sap pp?
Consignment matl how will be use
Explain what is prt (production resource tools) in sap pp?
Define mrp group
In tm, if a group of employees gets 10 days of annual leave, what will be the time evaluation status?
We need to do gi of components to production order using back-flush. The component stock is managed in batches. The batch to be back-flushed?
How do you integrate HR (employee) with PP?
Explain what happens to planned after it has been converted into production order?
If u maintain sub-contacting where and how will be reflect