what is the relation between seventh day strength & twenty
eighth day strength of cement concrete
Answer Posted / ravisobhan
7 days strngth is at 2/3rds of 28days stength. this is
required to check the concrete strength gaining in view of
removing formwork and to take preautionary measures incase
of failures before deshuttering.
| Is This Answer Correct ? | 33 Yes | 0 No |
Post New Answer View All Answers
why & what is perchatage we are using fly ash in concrete?
What is a bearing capacity of soil?
List out the types of roofs?
How do we calculate the power of centrifugal pump?
How and where are aqueducts built?
Describe the role of independent Quantity surveyor?
How to testing voids of filled aggregate in bitumen mix design
What are the different softwares used for cad?
Explain the mechanism of cavitations in pipes and drains?
CAN WORK WELL UNDER DEAD LINES OR PRESSURE?
how to calculate cost of raw materials of a building for 1000 sqft & also consolidated cost of labour in a 1000 sqft building
residential projects,structural.
how much used soil in 1 brick of standard size?
1. 1. The mass of a chunk of moist soil is 34 Kg and its volume is 0.012 cu. Meter. After drying in an oven, the mass reduces to 14.25 Kg. Determine the water content, the density of moist soil, the dry density, void ratio, porosity and degree of saturation. Take G = 3.25
how much cost of single coat 20mm thick plastering per sqre meter