As an engineer, what u should do when the construction of a
building doesn't meet the required specifications?
Answer Posted / narendra
a. If building is underconstruction
1. see if errors are seviour or not
if yes do reconciliation with experts
if not anlyse losses and make possible
corrections
2. if errors are serious reconstruct entire part or
whole but at any cost do not leave as it is. you can re
embers cost from others but not at the cost of structure
and human life which are supposed to dwel in it in future.
b. If building is complete
1. check the errors, whether are with immidiate
affect to stability of structure, if errors are serious
find solution with experts and immidiately do needful with
SOS situation.
2 if errors are causing no immidiate effect like
leakages, crcks, loose tiles etc. do reconciliation and get
the problem solved.
Any way, on top priority see that specification errors are
not affecting structural stability and then functional
stability and lastly aesthetic sence of the structure, in
nut shell.
2. If errors are not so serious
Is This Answer Correct ? | 8 Yes | 0 No |
Post New Answer View All Answers
give me the rate analysis for Bituminous Macadam and SDBC
CAST EFFECTIVE WATER SUMP CONSTRUCTION DETAIL
What is min thickness,min grade of conc & age of PQC ?
manhole height is 1500 mm and width of brickwork is 230 mm dia of manhole covering is 560 mm brick masonry 1:4 horizontal length is 1500 mm and plaster 12 mm thick on both side 1:3. how to estimate the quantity of brickwork with mortar cement and sand for manhole chamber.
Cut Linten (RCC-1:2:4)on 10" wall - what should be the width and hight of cut Linten? Secondly, 1 X 1.6 foot,4" thick window sun/rain shed (Chajja)should consume steel,Cement, sand and Stone chips?
What are advancements in civil engineering?
residential buildings,mixing of concrete,structural,construction material,site handling.
What is made from large rocks, which protects the base of cliffs?
hi every body..i have applied for RRB section engineers CIVIL.i wanna prepare for that,so can any one suggest me some books and where can i get the syllabus for this..i would be vry greatful if any one can help in this regard
How to calculate cement, water, fly ash amount for 1 cum if the w/c ratio is 0.4 and fly ash to cement ratio is 1:9
what is the use if we fixed butterfly ties in column and masonry work joint?....where we have to fix(distance)..
Explain what is Critical Path Method (C.P.M)?
a) we have 30nos., 300mm dia, 4m length double under reamed piles.calculate excavation quantity.b) tell concrete qty. also.
How many kilo-newtons equals 1000 kilogram?
What is the difference between absorption & adsorption and sorption?