What would be the ratio of a Delta-Wye tranformer having
48000 volts phase to phase on the primary and 4160 volts
phase to phase on the secondary?
Answer Posted / nain
voltage for delta side will b measured line voltage(phase
to phase)
voltage for star side will b measured phase voltage(phase
to neutral)
as u hav given both line voltages so for star side v will
convert that to phase voltge i.e.4160/1.73=2404.62
so ratio=48000/2404.62=19.96
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
why constant voltage transformer should be start without load? and if started then what will happen?
Explain M Var? Which types of problem occurs when reactive power increase at the time of full load of plant and at the time of synchronize of plant?
What is meant by stator?
How does zener phenomenon differ from avalanche breakdown?
how the CT and PT is connected in the circuit during testing of transformer explain with diagram
what is the main function of capacitors in mccs.
Why insulation level follows this order? transformer < bus bar < circuit breaker & Isolator < transmission line.
hi plz send me reliance placement papers..i.e electrical technical papers that have been asked in reliance test.
how to generator maintenance (A Check, B check,Etc)
Iin ESP why positive is grounded ? why not negative ?
Can any one provide the inspection procedure of MIMIC for VFD panel? Details: If someone wants to have a mimic in the VFD panel what are inputs considered for the mimic(like on,off,trip) whether we are able to add speed variation in the mimic(if so how can we get) and what are the parameters to be checked in the MIMIC during inspection?
I WANT TO know WHICH WAY IS BETTER FOR CONNECTION BETWEEN POWER TRANSFORMER AND MAIN DISTRIBUTION PANEL. 1-IS BETTER WE USE CABLE? 2-IS BETTER WE USE BUS DUCT? my transformer rate power is 2500KVA
What is d main advantage of using double circuit 3 phase transmission ?
i've iocl interview.. if you know the interview process please give me information..
hi friends ,iam working as genset AVR service engineer in electrical field from past 2 yrs throughout india . i plan to shift in some other job without travelling in same field because i con't travel,i dont know what i do for that so please guide me what job is suited for me,how i can serch the job please anybody helpme iam totally confused