Is it possible to block a material to be deliver from an
specific plant without block the creation of sales orders?
So in summary the material has to be blocked just for a
specific plant in the moment of delivery. One sales order
with different plants per line could be shipping except the
lines that contain this plantX
Thanks!.
Answer Posted / eldi
There is no direct way to block material for a plant at the
time of delivery. However we could use the MARC-MMSTA field
in MRP-1 view which can be checked during sales order
creation to block the line item for delivery. Another way
would be to move all material stocks in that plant to
| Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
Give me examples for Medium Priority & High Priority Tickets from your support project? Give detailed error message/ issue ,your analysis,finally how did you resolve that ticket along with detailed procedure & explanation and t-codes if any? I have an interview in immediate future so plzz help me...Please reply asap... Urgent!!!! Waiting for your response eagerly... Thanks in advance
Output with different language is it possible to have two delivery notes in two different languages?
What is the difference between pgi cancellation and returns order?
What are the views in a material master?
Define Product attributes?
What is rush order?
How can we configure Input Tax in SD?
What is incompletion log?
What are the responsibilities of a technical consultant in an implementation project?
Give a definition of plant (in sap).
What is the purpose of the sales document type?
can any one give one scenario of change request
Is anyone familiar with allocation run – Tcode is Arun_ITA?
What is sales and distribution (sd)?
Can you assign two different sales organization to the same company code?