my scenario is repetitive manufacturing (REM) make-to-stock
(MTS)production for sugar industry. What are the things, I
have to customize for this scenario, to the PP point of
view..

Answer Posted / manuel

This is a very large question, but I tried to resume it:

We supose you have the rest of Master data created (Work
Center, Bill of Material, Routing ) , so I will only
explain the differences;

1.- Material Master: You have to create Product Versions
(C221), add this information with MM02 to materials.

Also you have to Fill View MRP4.

2.- It's neccesary a Cost collector.

This a very

Is This Answer Correct ?    9 Yes 4 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Explain the process of Material costing.

1303


Are there any reports in sap to list of material requirement from ltp ?

727


What are traffic lights in mrp?

837


How costing is affected the pp?

696


What is standard order type

1857






Define gaps.

699


You want to integrate pp with fico. What steps would you take?

669


Explain how can you create production order without routing and bom?

704


What are the MRP master data?

1312


Explain the uses of the simple maintenance interface?

714


What are the types of MIC?

1309


Can't one material be assigned to more than one operation in a routing?

715


How is indian slab and us slab?

726


In the monthly lot size proc, how to generate lot at the end of Period?

3892


Mention how mrp (material requirement planning) types are classified?

783