my scenario is repetitive manufacturing (REM) make-to-stock
(MTS)production for sugar industry. What are the things, I
have to customize for this scenario, to the PP point of
view..
Answer Posted / manuel
This is a very large question, but I tried to resume it:
We supose you have the rest of Master data created (Work
Center, Bill of Material, Routing ) , so I will only
explain the differences;
1.- Material Master: You have to create Product Versions
(C221), add this information with MM02 to materials.
Also you have to Fill View MRP4.
2.- It's neccesary a Cost collector.
This a very
| Is This Answer Correct ? | 9 Yes | 4 No |
Post New Answer View All Answers
Are there any reports in sap to list of material requirement from ltp ?
Define 'sop' (sales & operations planning)?
What is the use of stock requirement list?
Explain service level agreements
Explain what is the meaning of exploding a bom?
Mention what are the production process in sap?
What is the use of t-code cs20 in bom?
What are dynamic actions? Give a few examples. What are it’s you used in them?
What is the difference between stock transport order and stock transfer order?
Mention what are the t-codes for creating, changing and summarizing bom?
What are the three 'mrp procedures'?
Difference between standard cost and variable cost.
What is the difference between “planned consumption” and “unplanned consumption”? Can safety stock calculation be done on either of these?
What do you do to run MRP for just one MRP Controller?
Mention how mrp (material requirement planning) types are classified?